Back to INDEX of reports
@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@
863
PART 5 -- CLOSING SUBMISSIONS, CONCLUSIONS, RECOMMENDATIONS
AND APPENDICES
------------------------------------------------
143. Closing Submissions -- -- -- -- -- -- -- -- -- 865
143. 1. Submission by Leshamstown Lane Residents -- -- -- - -- 865
143. 2. Submission by Mr. O'Donnell -- -- -- -- -- -- 866
143. 3. Submission by Alan Park, Bellinter Residents Association -- -- -- 873
143. 4. Submission by Brendan Magee, Meath Road Action Group -- -- -- 875
143. 5. Submission by Mr. Casey -- -- -- -- -- -- -- 876
143. 6. Submission by Peter Sweetman -- -- -- -- -- -- -- 888
143. 7. Submission by Mr. Butler -- -- -- -- -- -- -- 892
144. Application for Costs -- -- -- - -- -- -- -- -- -- -- -- 899
145. Issues Required to be Addressed under Sections 50 (2)
and 50 (3) of the Roads Act, 1993, as amended -- -- -- -- -- 899
146. Comments on Written Objections and Submissions
made to An Bord Pleanala, prior to Hearing -- -- -- -- -- -- 918
147. Comments on Submissions made on Legal Aspects of Council's Proposal -920
148. Comments on Submissions made on Route Selection, Consultation
and Information Aspects of Council's Proposal -- -- -- -- -- 927
149. Comments on Council's Application for Confirmation of
Motorway Order and Approval of Road Development -- -- -- -- - 931
150. Recommendations on Confirmation of
Motorway Order and Approval of Road Development -- -- -- -- 996
Table 1. Modifications to be attached to any Approval of the
Motorway Order under Section 49 of the Roads Act, 1993 -- -- 998
Table 2. Modifications to be attached to any Approval of the Road
Development under Section 51 of the Roads Act, 1993 -- -- 1002
Appendix 1. Names and addresses of Objectors
to Motorway Scheme Order -- -- -- -- -- -- -- 1008
Appendix 2. Names and addresses of Persons or Organisations
who made Submissions to the Road Development -- -- -- 1026
864
Appendix 3. Names and addresses of persons
represented by M/s Gaynor Corr -- -- -- -- -- -- -- 1030
Appendix 4. Documents handed in to Hearing -- -- -- -- -- -- -- 1036
Appendix 5. List of Wayleaves to be Acquired -- -- -- - - -- -- 1051
Appendix 6. List of Public Rights of Way to be Extinguished -- -- -- -- 1052
Appendix 7. List of Private Rights of Way to be Extinguished -- -- -- -- 1057
Appendix 8. List of Planning Permissions to be Modified -- -- -- -- -- 1059
-----------------------------------------------
865
143. Closing submissions :
143. 1. Closing submission by Leshamstown Lane Residents :
This was made by Jimmy Finlay and Brendan Murphy on Day 23 of the Hearing and a
copy of their submission is listed at Day 23 in Appendix 4 of this Report.
Mr. Finlay said that they would like to focus on what they had been discussing with the
Council since their previous visit and said that arising from the Inspector's comment then
they had focussed on two issues. He said that the first issue was the costing of a bridge
over the M3 at Newalls and some traffic calming issues at Leshamstown Lane. He said
they were given sight of an outline sketch of a bridge but were told that it was
questionable if a two-lane road could be put in, due to the limitations of the CPO on the
land required there.
He said most of the discussions and communications with the Council had been about the
Leshamstown Lane issue and they had received certain documentation in the past week
which was an outline of what might be possible. He said that in fairness to the Council
officials who were trying to assist them in resolving the crux, the documentation was not
a definitive view by the Council but he said that it would be a sort of a carving up of
Leshamstown Lane in such a way that it might be able to accommodate the diverted
traffic from the Drumree Road after the road was severed. He said the proposals were to
have entrance ramps at the Drumree and Dunsany ends of the Lane with eight further
ramps spaced out along the Lane and with lighting at each ramp and that there would be
eight pull-in points as well.
Mr. Finlay said that at a meeting attended by over 100 residents of Leshamstown and the
surrounding Drumree areas on the previous Monday there was shock and horror at what
was being proposed as these proposals were a sort of mini-urbanisation in a rural setting.
He said while they might be suitable in a suburb of Dublin the residents did not see this
as something that should be tried out on their locality. He said they could not accept what
was the result of bad planning and a lack of consideration and said that the EIS made
virtually no mention of the impact this would have on their lives. He said the decision to
sever the road had severed a community and split a parish from its hinterland. Mr. Finlay
said that the Council were saying that they were going to force traffic up Leshamstown
Lane however difficult that was over 800 yards but were not going to give them a bridge
of 100 yards at Newalls which would restore the link between Drumree and
Dunshaughlin that had existed for hundreds of years.
He said that the people at the meeting were up in arms about what was being proposed by
the Council, that they had not opposed the M3 proposal, they had not opposed the
sewerage works and they had not opposed the roundabouts which would flyover the M3.
He said that if the Council thought the residents would accept a motorway in their back
866
gardens and a mini-O'Connell Street along their road, they had better think again. He said
they felt it was up to the Council to resolve the issue of how they were going to take the
rest of the traffic in.
Mr. Finlay said the traffic in their area was made up of people coming home from
Dunshaughlin through Batterstown to avoid the traffic jams in Dunshaughlin; people
from Trim used their road and locals who lived in Drumree Village used it. He said these
were three separate groups who used the Drumree Road and the new feeder link would
have no use for those except for people coming back from Dublin who came on the
motorway. He said there was no need for the people living around the Drumree area for
this link road as it was too much of a roundabout journey for people to use it as they
could be faced with bottlenecks coming across the motorway . He said that it would only
be the people from Trim that would use it and that it was a waste going ahead with a road
that two-thirds of the people would not use.
He said that if it was a farmer who had land on both sides of the motorway he would be
given an overpass and they as residents should get the same treatment when they wanted
to stay in contact with their mother town, Dunshaughlin. Mr. Finlay said they were
annoyed that sufficient land was not kept in the CPO to allow this bridge to be built and
he said they felt this was done deliberately so that there could not be a case made to have
a bridge built there in the future. He said that even if the bridge was only wide enough to
take one car at a time this would be only over 100 yards, when the Council were sending
them down 800 yards over a single lane road. Mr. Finlay said they hoped the Inspector
would take on board the unfairness of what had happened and said they were not asking
for the M3 to be stopped but were asking that the 100 yard span be kept open to keep
their communities alive. The Inspector said the points they had made would be taken into
account.
Mr. Finlay asked if they could engage with the Council in open debate at the Hearing on
some of their concerns and the Inspector said that, while there was nothing to prevent
them from having further discussions with the Council, they had been given a second
opportunity to make a submission and the Hearing was not going to become a mediation
forum at this stage for this matter. Mr. Murphy asked if the Council could give the
reasons why the bridge could not be put in and Mr. Keane said they would write to
Leshamstown about that.
143. 2. Closing submissions of Michael O'Donnell B.L.
on behalf of his various Clients :
Before making his specific submissions, Mr. O'Donnell referred to the issue of
accommodation works which he said was of concern to some of his Clients and said he
accepted the Council had some difficulties because of the nature of their proposal and
with some aspects being left to the contractor to design, but said he thought there should
be some degree of precision as to how mitigation works were to be included and that
these should be given to the Hearing so there would be some degree of certainty on what
867
formed part of the scheme. The Inspector intervened and said that the precise details of
accommodation works were not an issue for An Bord to decide on, but said that he
accepted there could be some more certainty in relation to what could be regarded as the
residential aspects of the frontage proposed to be acquired. He said this was part of the
reason he had sought clarification on that issue from Mr. Bergin.
Mr. O'Donnell said that in relation to the case of Mr. & Mrs. Peters, the Council had
fairly accepted the impact would be severe since the house would be located within 50
metres of the boundary of the works and said that, while this was not the actual
motorway, there would be severe disruption during construction for his Clients, and he
suggested this would almost make it impossible for them to live in their house for the
period while the road was being constructed. He said the house had been laid out to a
very high standard but that it was now going to be very susceptible to the road intrusion,
particularly from traffic noise, since the living rooms and bedrooms were at the front of
the house. He said that no mitigation measures were proposed either for during
construction when the impact of dust and noise would be very significant, or for the
operation of the road when noise levels would be a major intrusion on their quality of life
and the amenities they enjoyed in their property.
He said that he was not going to review the evidence given about the noise impact but
said that the appropriate levels were those imposed by the Council itself, by An Bord and
by the EPA for developments where they imposed noise conditions. He said that a
substantial stone wall should be included as a condition to mitigate the impact of noise,
dust and visual intrusion along the full frontage and said this should be constructed before
work commenced on the road development. He said that the landscaping works should be
time limited so that they were completed within the planting season after commencement
of the works so these could be in place to mitigate the impact on the house. He said that,
without meaning to be facetious, if a badger sett or bat colony were as close to the route
as the Peters house was then it was likely the route would have been moved and he said
the Peters were entitled to get at least the same degree of consideration and protection
when they would be continuing to live so close to the road.
Mr. O' Donnell the referred to the Tara Stud situation and said the Council witnesses
had also fairly acknowledged the major impacts there would be on the operations of the
stud which would seriously undermine its ability to continue since it was effectively
losing one third of its land between the 100 acres severed, the 70 acres taken and the
lands sterilised by being in close proximity to the motorway. He said that Mr. Osbourne
had acknowledged the status of the stud as a nationally important stud farm and Mr.
Bergin had given the example of the National Stud where there had been a bunding with
a wall and appropriate planting of mature trees provided along the full length of the
boundary. He submitted that a stone wall constructed along the full length of the
motorway should be required as a mitigation measure in the Tara Stud situation and said
that this would go towards mitigating the traffic noise and general construction impacts
which would be very inimicable to horse rearing and horses breeding activities.
868
He said that in the case of the Swans, both Mr. Osbourne and Mr. Guthrie had fairly
accepted that the planning permission there would be un-implementable since the
motorway would have an impact on the proposed house and stable block. He accepted the
issue was primarily one of compensation but said the impact would appear to be very
severe in terms of the Swan lands.
Mr. O'Donnell said that in terms of the McCarthy lands at Garlow Cross the impact on
that property was similar to that in the Peters case as the road would come very close to
their house but there was the addition of a major interchange being located in close
proximity. He said the construction works associated with the interchange would have
major negative impact on the house during both construction and operation and he
submitted that appropriate mitigation measures should be required to limit and, if
possible, eliminate those impacts. He said that the light pollution would have a serious
impact on the McCarthy lands at night and said that regard should be had to this in terms
of the amenity of the McCarthy family home and also on his stud farming operations.
Mr. O'Donnell said he was hopeful that some of the difficulties identified in the case of
Betty Newman Maguire could be resolved by the Council and that they might be able to
indicate before the end of the Hearing some proposals that might deal with some of her
concerns. He said that in the event that this was not possible, he submitted that her
requirements were reasonable, particularly her request that appropriate landscaping
would be carried out along both the new county road and along the embankments to the
proposed motorway and that appropriate noise mitigation measures be included on the
bridge. He suggested that these should include installing porous asphalt to reduce the
noise impacts.
Mr. O'Donnell then made an application for his Clients costs of the Hearing and said that
he was aware of the Inspector's position of this not being a matter for him to deal with,
but said he simply have it recorded that the application was made as none of the
submissions were frivolous and he suggested they might have provided some assistance
to the Inspector in making his recommendation to An Bord.
Note -- Mr. O'Donnell's submission on behalf of Dalgan Park was made on the
following day, Day 25, to those made on behalf of his other Clients.
Mr. O'Donnell commenced by saying that there was something unbelieveable about the
entire proposal for the Dunshaughlin to Navan Section since if you said to someone who
had no particular knowledge of the area that the Council and the NRA were proposing to
build a tolled motorway that crossed an internationally important river at a crossing point
where that internationally important river, the Boyne, and a similarly important river, the
Skreen, converged, they would find that extremely surprising. He said if you told them
the river system had species protected under the Habitats Directive and was a proposed
SAC and a major spawning ground for salmon, they would be amazed. He said that if
you then said that this immediately adjoined the lands of Dalgan Park, which had been
acknowledged as a landscape of outstanding beauty, with trees specifically protected by
the Council and used as a public park, it would be almost unbelieveable. He said that if
869
you then were told of the major educational and pastoral facilities, the retirement home
for old people and the range of facilities which would be adversely impacted in a major
way by noise, construction impacts, traffic, it would be scarcely believeable that this
could be possibly chosen by the Council to locate this roadway.
Mr. O'Donnell said that, as if that was not bad enough, on the other side of the lands was
a world famous site for archaeological reasons that the Council through Ms Gowan
accept the road would have a profound impact on and he said that, when all of that was
put together, this Dunshaughlin to Navan Section was all about the impact the road would
have on this "landscape" and he said he used the word "landscape" metaphorically for all
that was contained within it. He said there was the archaeology which was clearly an
international issue as it was the most sensitive site in the country and that proposing a
tolled motorway at the bottom of the hill within 1000 metres of what Ms Gowan called
the complex of Tara itself was an extraordinary proposal. He said that when this was
combined with the landscape, the river system, the public park in Dalgan Park, the sacred
nature of that place, the links of Dalgan with Tara, it was incomprehensible that a such a
design would be proposed. He referred to the Interchange at the bottom of the Hill of
Tara with its lighting giving constant light pollution, the noise and traffic, and said the
scale of what was being proposed was unacceptable.
He said that when you stood on the Hill of Tara and looked north or west, you looked
across a landscape that had remained unchanged for 2000, or perhaps 3000, years with
the link from Tara to Skreen, from pagan to early Christian and to modern Christianity in
terms of Dalgan Park. He said the landscape was a stunning, mythological,
archaeological landscape of great scientific and ecological value that was effectively
unchanged with the existing roads that had followed traditional pathways and changed
incrementally overtime. He said that what was now proposed would radically change the
entire context of Tara and the landscape and would destroy that landscape forever. He
said that it could never be the same and that when you stood on the Hill of Tara and
looked north to Skreen you would look across a major interchange and a tolled motorway
system, which would be the destruction of the landscape forever with no going back. He
said that this generation would have destroyed the landscape that existed unchanged for
3000 years by the construction of a tolled motorway system and a major interchange and
he submitted that this was not something that could easily be forgiven, if it were allowed
to occur.
Mr. O'Donnell suggested that no answer could be given if someone asked in 10, 15 or 20
years time "why was this motorway and major interchange allowed to be built within the
Tara complex to destroy that landscape" since it was simply unacceptable and he
suggested that now was the time to stand back and consider what was being proposed. He
said there was nothing to justify it when the scale of what was being proposed and the
landscape were considered. He said that there was not even a public service development
justification since it was a private profit making development that was being proposed to
be designed, built and operated by a private contractor, which would be designed for
profit and used as a parallel system to the existing road which would remain for those
who could not afford to pay the tolls. He said that it was for that type of a development
870
that we were willing to destroy the landscape along this location. He said it was clearly
not just a national question for this development because it was a world site and so was
an international question.
He said that Tara was for him the symbol of Meath and it was Meath County Council that
were now proposing this development, which would on their own evidence have a
profound impact on Tara. He said that not only would it destroy Tara but the Council's
answer for the monuments that had been identified as being connected to Tara was that
they would also be destroyed or, he said, by the euphemism quoted the previous day they
would be preserved by record. He said it was a wonderful answer for Tara that it would
be preserved by record and could then be visited in the library where there would be
drawings to show what had been removed and what had been destroyed. He submitted
that preservation by record was not an answer in this case and said that the Council had
prepared the EIS and purported to rely on that answer to some extent as the justification
for their case to proceed with this route.
Mr. O'Donnell said that in all of the Hearings he had been involved in, he had never seen
a submission that was so lacking, so inept and so inadequate. He referred to his
submission to the Inspector during the Hearing that he should go to An Bord Pleanala and
ask them to consider if they should proceed with the Hearing in view of the inadequacies
of the EIS as, he said, it was that bad. He said that it might not matter if the site and lands
were not so important but this was a critical site and he said that any flaws of deficiencies
were magnified because of the scale and the impact of what was being proposed. He said
that the inadequacies in the EIS were of crucial importance in this case and suggested that
Mr. Guthrie as the Project Engineer was not aware of the geographic, administrative or
legal context in which he was operating nor of the SPGs and said this level of ignorance
pervaded the EIS which accepted that the design had not yet been formulated and that it
was a matter for the contractor to agree the detail of the design.
He said that you could not accept a document for such a sensitive site where the design
was not yet formulated and where it would be left to the contractor to source the materials
for filling and the source of extraction and waste materials, where culverts and bridges
had not been formulated and where the height the road would be built was not even
known and said that was what was being proposed for this landscape of international
importance from at least five different criteria.
He said that the only part of the report that was generally immune from criticism was the
archaeological section since this clearly accepted the profound impacts that the
development would have, but he suggested that even here it was incomplete since Ms
Gowan had indicated that a major site, identified as part of the preliminary works, would
be destroyed as part of the development.
He said that for the built heritage Mr. O'Sullivan did not know the legal context within
which he was operating and was not aware of the need to consider the curtilage of a
protected structure, had no idea of what he was required to investigate and accepted that
871
he was simply sent to look at buildings without making any critical analysis of them
which, he said, gave a built heritage that was fundamentally flawed.
He said there was the ecology report on an internationally important river system where
the person preparing that report did not disclose the proposed SAC --- the highest
designation the EU could give to a site, he was not aware until it was put to him of there
being three separate species protected under the Habitats Directive in the river system,
and all of that was within the area where there was, he said, a major intersection of a
county road with the motorway being constructed at the confluence of two rivers.
He said there was a noise report by a person who had never visited the site until after the
EIS had been published. He said that when the impact of noise on the context of Tara
was considered and that Mr. Summers had never visited Tara and did not know what it
looked like, never visited Dalgan Park and did not know it was a public park before he
had prepared his report, and that this was what put in evidence as something to rely on to
justify the proposed route was unbelievable arrogance and contempt for a landscape and
for the people that lived there and for the heritage the EIS was required to protect.
He said there was a discrepancy in the air pollution report of about 20 times difference
between the modeled and measured air pollution levels with no explanation of how this
could have occurred from Mr. Crawford, the air pollution expert. He said the landscape
expert argued he could screen or landscape away a major interchange which was again a
contempt for the ordinary common sense view of what the likely impact was. He said that
there was a socio-economic report by Mr. Prendiville who accepted that he had no
sociological or economics expertise yet purported to give evidence on socio-economic
impacts.
Mr. O'Donnell suggested that for each category of evidence there was a huge inadequacy
and discrepancy with huge holes in what had been submitted and said that if a script were
to be written for ineptitude and inadequacy, a more disparate and inept number of people
could not have been chosen. He submitted that when the Inspector looked at the evidence
he had heard, then he could not rely on what had been stated in this section of the EIS. He
said that of all the landscapes possible, this one was the most critical for such mistakes to
be made and that to have prepared and relied on such a document made it not surprising
that they chose to build an intersection in this particular site in an EIS that was so
fundamentally flawed. He submitted that it was simply not possible to allow the damage
that would happen in this case to occur and said that of the range of experts, and he
named them all, not one could stand up and say that their report was complete and
accurate and free from flaw. He said the contrary was the case because each one was
hugely deficient, inadequate and had been shown to be such.
Mr. O'Donnell then said that there was an alternative and that it had been said on
numerous occasions to the Hearing that for this section of the route you looked at the
proposal to the east of Skreen. He said that he had deliberately chosen to compare these
two routes and that on each heading they were either equal or the road east of Skreen
was better. He said that for air pollution they were probably equal but that it would be
872
better not to cause air pollution to a world heritage site or a public park so the route east
of Skreen was the better choice. He said that in archaeological terms it was accepted the
road east of Skreen would be less damaging than a road through Tara and that in terms of
built heritage there were no protected structures east of Skreen. He said that for ecology
while you would have to cross the Boyne, this would not be at the confluence of the
Boyne and Skreen and that spawning would be protected, which made east of skreen
better. He said that in landscape terms Mr. Burns accepted both were attractive but
clearly a world archaeological site had a particular impact and should be avoided in
landscape terms. He said that in terms of noise and vibration a public park and a world
heritage site and a centre like Dalgan Park were places to avoid in terms of excessive
noise levels.
He said that the only section that sought to be relied on in providing a negative impact in
the Tara to Navan section was the socio-economic impact and, he said, this was by a
person who had no expertise in this area at all and his evidence must be discounted
because of this. He said that it had been shown to the Hearing that the entire basis of the
approach was fundamentally flawed and he submitted that if the two routes were looked
at objectively in the terms set by the Council then the road east of Skreen was the
preferred option. He said there had never been a satisfactory explanation given why that
route had not been selected and said that it came down to whether the EIS could be
depended on and said it was his submission that it could not be given reliance. He said
that even if reliance were to be given then the route in the EIS was not the optimum
because he said it could never be the case that you could build a motorway through Tara
and a major interchange at the bottom of the hill where Tara begins and that it could
never be right to build a motorway through a public park.
Mr. O'Donnell suggested the answer for that was because the public park and the uses
within Dalgan Park were never identified in the EIS and said that nowhere within the
EIS were the range of activities and public nature of the facilities in the uses of Dalgan
Park ever identified, so they were not had regard to. He said that if the Council had
directed its mind to those uses he had no doubt that they would not have chosen the route
they did as they would have been aware of the significance of the Boyne and Skreen
rivers. He said that had they been aware of the full extent of the archaeology and its
impact on Tara, he had no doubt that they would not have chosen that route and he said
the EIS was so flawed that it was not surprising they chose to proceed with that route. He
said the Council's solution was to destroy Tara because, quoting from the McGarry v.
Sligo County Council Supreme Court judgement, he said destroying a monument likc
Tara was not just the monument but its context and if its context was destroyed, you
destroyed the monument.
Mr. O'Donnell said that if a motorway was run through a public park at a place used by
the public then this effectively destroyed the public park, that if you built a major
intersection across a river spawning area you put that to an unacceptable level of risk and
that if you put all of these together you had a recipe for disaster. He said that could never
be confirmed by An Bord Pleanala if they were to properly direct their mind to what had
been proposed here. He said the Council might reply that they would destroy significant
873
amounts of landscape, archaeology and ecology but that they would preserve these by
record and he said he would conclude by saying that if the record was anything like the
record contained in the EIS, then it would bear no relationship to what was, in fact, there.
He submitted that having regard to the evidence there was only one solution for An Bord
Pleanala and this was to refuse to confirm this section of the road and he further
submitted that this was the appropriate recommendation for the Inspector to make.
143. 3. Closing Submission by Alan Park on behalf of
Bellinter Residents Association :
Mr. Park said that the main thrust of the BRA position regarding the proposed motorway
was, and remained, their disagreement and dissatisfaction with the Route Selection
process as they believed this process did not fairly assess the various options and that the
wrong conclusion had then been reached. He said they had demonstrated that the
preferred route of those who had attended the Public Consultation process was ignored
and that the EPR was the second least preferred and he said the Corridor Selection
process was never put to Public Consultation which, he said, meant that the process was
not correctly followed.
Mr. Park said there were many areas in the Summary Matrix in Table 4.2 in Vol. 2 of the
EIS that were not correctly rated. He gave details of these which included :-
1. The impact on "minor roads" rated as "slightly positive" which they disagreed with
and referred to the extra length for his neighbours in walking to Dalgan Park from
their homes or to the shop at Garlow Cross, where a longer round journey of 5.1 km
compared to 3.9 km would now apply.
2. He said that the Landscape & visual impact for the EPR (Blue Route 2) had been
wrongly entered in Table 4.2 and that the value given was understated and referred to
the values shown in Table RSR/6.6.1 as being the correct ones, and he said that Mr.
Guthrie's response in cross-examination was erroneous.
3. He said that both Consultant Archaeologists had clearly reported that any route
between Tara and Skryne Hills was not a desirable option and that this was supported
by Conor Newman and he suggested that Duchas were also opposed to a route
through the Tara/Skryne valley and said that they believed the EPR was Route P. He
referred to the failure to include the geophysical survey images in the EIS and
suggested that this could only have been done to conceal the full facts. He said that
the BRA believed a route through the Tara/Skryne valley should be avoided at all
costs.
4. He criticised the impact on private properties in the Residential/Private Property
category in Table 4.2 of "moderately positive" saying that there was no positive
impact on the properties in Bellinter, Ardsallagh or Cannistown and said this entry
was erroneous.
5. He said it seemed the Community Impacts were almost forgotten with no mention
being made of Dalgan Park or Dowdstown demesne in the socio-economic section,
nor of the impact on the walks in Dalgan Park by the Rivers Boyne and Skane, nor of
874
the work and courses carried on in Dalgan Park and Dowdstown House and said that
part of the EIS was not adequately addressed.
6. He said that they were as confused by the Noise section as the expert, Mr. Summers,
seemed to be. He said that some of the figures presented were incorrect, that the
manner in which readings were taken was open to doubt, that Mr. Summers only
visited the site for the first time in August 2002 after the EIS had been published and
that the Council were now saying that a new noise criteria would be adopted to assess
the noise impact. He said that the BRA saw no alternative to a complete reassessment
of the entire noise section in the EIS to provide correct values for Table
4.2 of Vol. 2.
He said that the BRA found Table 4.2 of Vol. 2 of the EIS was not a true and accurate
assessment of the impacts and submitted that the values in that table should be corrected,
which could then change the conclusions of the selection process.
Mr. Park said they were not satisfied that the provisions for the railway line at
Cannistown had been adequately provided to meet the requirements of Iarnrod Eireann
and said that the railway line should not be economically disadvantaged by having to
construct a bridge over the motorway. He said the railway connection was an important
part of the CDP and the SPGs and deserved to be considered as part of an integrated
transport plan for the County and not as a sort of optional extra that might be taken up in
the distant future.
Mr. Park referred to the response given by the Council to the BRA objection to the EPR
and said that the only issue of substance in it was a description of the bridge crossing the
River Boyne, with every other aspect of the issues they had raised being ignored. He said
they considered Mr. Harold O'Sullivan's response inadequate; that of Mr. Burns was still
awaited; that they had problems with Mr. Summers credibility; that the MC O' Sullivan
response on Blundellstown & Cannistown Interchanges failed to mention Blundellstown
and said that the Halcrow Barry response described the topography of Blundellstown
without explaining the rationale for that Interchange.
Mr. Park concluded the submission by saying that the BRA had found the experience to
be less than satisfactory; that they had found it most difficult to get full and proper
information about their queries and fears; that they had found many answers to be
economical of the truth and that they had not been given full and free access to
information they had legitimately requested and they felt advantage had been taken of
their inexperience and lack of knowledge in this field. Mr. Park said that to defend their
own interests, property and environment they had been forced to spend considerable time,
effort and money in pursuing their case and he asked that An Bord Pleanala would look
sympathetically at their right to recover costs and expenses incurred with the Hearing. He
said that the BRA appreciated the Inspector's forbearance relating to their presentations
and cross-examinations as they were made to feel at ease in an area where they were
inexperienced.
875
143. 4. Closing Submission by Brendan Magee on behalf of
the Meath Road Action Group :
Mr. Magee said that the MRAG objection to the proposed M3 was based on their
assertion that the wrong route had been chosen. He said that the EIS was a very well put
together document and that, taken at face value, it was difficult to find fault with it. He
said it was their contention that it was a flawed document, since it dealt only with the
Preferred Route, and that of deliberately hid the fact of another route option being more
viable from an environmental and cost point of view. He said that, in spite of the
Council's efforts to prevent the MRAG getting information about the proposal, they had
managed to get enough to be able to prove that the wrong route had been chosen and said
that he would now summarise this proof, which had been exposed during the crossexamination
of all of the Council's experts.
Mr. Magee said that the MRAG instinctively knew that the wrong route had been chosen
when it was proposed to be located between the Hills of Tara and Skryne through the area
with the highest concentration of known archaeological sites and said that this had been
proved when they got copies of the Route Selection Report, The Archaeological
Assessment Paper Survey by Valerie Keeley and the N3 Navan to Dunshaughlin Route
Selection by Margaret Gowan. He referred to neither of the archaeological reports
recommending the Preferred Route and Ms Gowan's evidence under cross-examination
of Route P being the most viable from an archaeological perspective. He also referred to
Conor Newman's presentation, the geophysical survey results and his opinion of the
archaeological dimension of the EPR going to be hugely expensive in time and money.
He then referred to the various expert witnesses for the Council and the Ecology, Air
Quality and Landscape & Visual sections in the EIS and said that a reading of their EIS
reports would give the impression that the Preferred Route was the "right" option but
when the same experts report in the Route Selection Report was read you found that
another conclusion was reached and that the preferred route was not the best option from
the perspective of that discipline. He said that there was no assessment made of the Built
Heritage in the Route Selection Report and that Mr. Guthrie had not disagreed with the
quotation from that Report which said that route P did not come close to structures in the
area. He said that the Noise figures in the EIS were admitted to be wrong by the noise
expert and asked what legal standing had an EIS when it had been proved some of its
information was wrong.
Mr. Magee submitted that none of the environmental experts employed by the Council
had recommended the Preferred Route and said that 5 of them had recommended another
route, Route P. He submitted that the decision to ignore all of the experts advice was
taken by Mr. Alan Guthrie as the Project Co-ordinator, and said that Mr. Guthrie had
justified his decision by saying that the primary reason was that the Preferred Route
affected fewer people. Mr. Magee submitted that the Assessment Matrix used to assess
all route options was proven not to have given any serious consideration to the effect on
people in the selection process, with the rating being shown as " slight positive" for all
options.
876
Mr. Magee said that Mr. Guthrie's only stated reason for not choosing Route P was its
remoteness from the N3 and he said that was not true, since the P route crossed the N3
only 2 miles from Navan, while the proposed junction at Blundellstown was 4 miles from
Navan. Mr. Magee questioned the location of a junction at Blundellstown on safety
factors because of the history of fatal accidents on the existing N3 between
Blundellstown and Navan which, he said, would also be added to from the increased
traffic using that section of the N3 to access the motorway.
Mr. Magee said there were a number of questions to be answered by Mr. Guthrie which
included why the NRA guidelines for Public Consultations were not followed ? ; why
were the Public's views expressed at those Consultations ignored ? ; why was
information not made freely available to the public ? ; why were documents changed and
edited before being made available to the public ? and why was false information given
to the public.
Mr. Magee said that, having heard the evidence, the MRAG believed that the Inspector
could not recommend that the route be approved, particularly the section going through
the Hill of Tara area. He said that the MRAG were not against a motorway but were only
against the proposed location and he said that they had put forward a credible alternative
that had many advantages over the present proposal. Mr. Magee concluded by asking that
a full feasibility of the MRAG Alternative Route Proposal be undertaken by the
NRA/Council before any final decision was taken.
( Note -- A hard copy and CD of the previous MRAG submission on Day 17 was handed
in by Mr. Magee and are listed in Appendix 4 of this Report at Day 25. )
143. 5. Closing Submission by Greg Casey, Solicitor,
on behalf of Sarah Maher, Ardbraccan House, Navan :
Mr. Casey said that he would start with what he would loosely call the Facts and that Fact
No.1 was the requirements for assessing needs for motorway schemes in the NRA
Guidelines which, he said, were quite strict. He said he would outline the chronology of
events that followed from when they had made a telephone request to the Council on 12
November for the completed Phase 1 & 2 questionaires returned to the NRA for this
scheme as required under the 1999 version of those NRA Guidelines and were told they
would be faxed to them. He said that by 18 November when no FAX had appeared they
again phoned the Council and spoke to Nicholas Whyatt and were then told that they
could not have these questionaires since " They" whoever, he said, "They" were had met
and decided the public were not entitled to see these under the Freedom of Information
Act due to commercial sensitivity. He said that on being reminded that access to
Information on the Environment under 90/313/EC and the Irish Regulations SI 125 of
1998 applied here, Mr. Whyatt had replied that this had also been debated and the request
was still being resisted but had requested a written application. Mr. Casey said they sent
off their written request on 18 November and repeated this at the Hearing on 19
877
November and that, in fairness to Mr. Whyatt, he supplied a letter to them on 20
November that explained the 2000 NRA Guidelines were in Draft form and the NRA did
not require that Phase 1 & 2 questionaires to be completed. He said they reminded Mr.
Whyatt that the 1999 guidelines were quite specific and would have applied at route
corridor stage, and said that Mr. Whyatt doubted these existed but had returned at 6.30
pm yesterday (20 Nov.) with those 1999 Guidelines.
Mr. Casey then read the Council letter of 20 November 2002 "--- I resume the
questionaires you referred to are those contained in the NRA Project Management
Guidelines (PMG), March 2000. You should note that these non-statutory guidelines
were not in place when the consultants were originally appointed to design and develop
the section of the scheme relevant to Ardbraccan House. Generally the PMG were
published when the majority of the sections of the scheme had reached the constraints
study, Phase 2, and route selection, Phase 3, stages of development. After publication of
the PMG, the Council consulted the NRA about their use in this scheme including the
completion of the questionaires. The NRA informed the Council that on the M3 Clonee
to North of Kells scheme they only required formal submission of the questionaires for
approval for route selection Phase 3 and that there was no need to get retrospective
approval for Phases 1& 2. Therefore there are no completed Phase 1& 2 questionaires for
any section of the scheme that were submitted to the NRA for formal approval. The one
exception to this is the Kells to Carnaross section which lagged behind the remainder of
the scheme. When the PMG were published, formal approval was needed to proceed to
route selection. Phase 3 for this section of the scheme was obtained from the NRA.
Notwithstanding the foregoing, our file does contain a completed Phase 2 questionaire
from MC O'Sullivan for the Navan by-pass section and from Halcrow Barry for the
Dunshaughlin to Navan section. I attach a copy of the Navan By-pass Phase 2
questionaire for your information. However, I would reiterate that neither of the Phase 2
questionaires for the Navan By-pass or the Dunshaughlin to Navan section were
submitted to the NRA in accordance with the PMG."
Mr. Casey said he was proposing that the Road Scheme Development Guidelines of May
1999 be submitted to An Bord to peruse at their leisure since Phase 1 as set out in the
guidelines was a pre-planning questionaire that set out in outline what the Local
Authority wanted to build, be it a motorway or whatever, and then, he said, the NRA
responded to that and sanctioned the Local Authority to go to Phase 2. He said they knew
these were non-statutory guidelines but they were guidelines that the NRA imposed
stringently relating to road planning. He said that the purpose of the Phase 1 questionaire,
which he said would only take about 10 minutes to complete, was to allow the Council to
proceed to Phase 2 and that was not funded by the NRA. He said Phases 2, 3 & 4 were all
funded by the NRA and that it was clear this particular scheme would be funded in its
entirety by the NRA, whether that was by a PPP or otherwise.
Mr. Casey then discussed the Phase 2 questionaire for the Navan By-pass which, he said,
had not been approved by the NRA but mirrored the Phase 2 questionaire set out in the
May 1999 guidelines and said that the questions answered mirrored largely the concerns
that Ms Maher had been enunciating to the Council and the NRA throughout the year and
878
this Hearing. He referred to the questionaire having been signed by Ms Joyce and said
that the questions covered were " field checked, streams, rivers, canals etc having regard
to drainage systems, local knowledge" both ticked yes; " springs, wells, watertables,
turloughs " it said "no information on wells". He said it said something relating to
turloughs, something about farm walkover aerial photography and preliminary site
investigation undertaken and otherwise no. He said that in relation to ground water the
answer was no and that written after that was " preliminary investigation undertaken". He
said that at "R" was asked " Has a review of Irish /EU legislation/ regulations relating to
infrastructure/funding/regulations been carried out, ie to include issues relating to
licensing requirements during construction, quarries, tips, mobile plants etc" and said the
answer was no. He said the answer to a question " are there known areas of special
designation within 10 kms. of the study area at B" was yes and that it referred to the NHA
on the Boyne and archaeological sites at Tara and he referred to the Navan By-pass as
not going near Tara.
Mr. Casey then said that from the 1999 Guidelines once the NRA gave the go-ahead, that
the first thing to be done was to draw up a Constraints Report; that the second thing was a
Corridor Selection Report; that the third thing to happen was the Route Options Report;
that the fourth thing was there should be a Route Selection Report and the fifth thing was
that the Emerging Preferred Route (EPR) should be produced. He said that it would be at
that point that the Members of the Council would approve the EPR which then went to
pre-planning stages and EIS and on the a Hearing like this one. He said that having set
out what was the correct chronology, he would now look at what the actual chronology
was which, he said, had been dug out during the course of the Hearing. He said that the
first thing considered appeared to have been in February 2002 (as he said it) and was
called Route Options; that the second thing appeared to have been considered in May
2000 and was the Constraints Report with Archaeology February 2000 and Architecture
April 2000; that the third thing considered appeared to have been a powerpoint
presentation to the Meath Councillors where the EPR popped up on the screen; that the
fourth thing, which he said was in its right order, was the Route Selection Report in
December 2001 and that the fifth thing was the Corridor Selection Report that arrived in
January 2002.
Mr. Casey said that as he understood it the Corridor Selection Report should have arrived
before the Route Selection Report and that the Corridor Report was dated January 2002
which was after the date of 19 December 2001 when the Council had advertised their
intention to vary their CDP and the Navan Environs Plan to allow for the construction of
a motorway incorporating the route west of Navan through Ardbraccan up to Kells. He
said that the Corridor Report arrived after the variation was advertised and that the Route
Selection Report, which was dated December 2001, should have arrived after the
Corridor Selection Report but said that by the time the Corridor Selection Report was
there it was already a fait-accompli as far as the 2001 CDP was concerned. He said that
the Route Selection Report of December 2001 and the Corridor Selection Report of 2002
had only been made available at the Oral Hearing.
879
Mr. Casey said this juxta-positioning of the planning such a project defied all logic and
had placed members of the public in County Meath and in particular, his clients the
Mahers, in a material disadvantage which he would now deal with. He said that the
Meath CDP of 2001replaced the 1994 CDP, which had been allowed an extension of time
by the Minister to allow for debate and for the public to be consulted, and that Plan
became operative in March 2001. He said that March 2001 was ten months after the EPR
for the motorway had been shown to the Members of the Council at their meeting on 8
May 2000 and that a Matrix ( which he showed to the Hearing) had been shown to the
Councillors at that meeting. He said he believed that the matrix shown to them was a
simplified version of the actual matrix for what reason he did not know, but suggested it
was to keep them "in the dark".
He said that between May 2000 and March 2001 when the CDP was adopted nothing had
been done to incorporate the EPR into the CDP and that this required the advertising of
the Variations on 19 December 2001, both to the Meath CDP which was 8.5 months old
then, and to the Navan Environs Plan and he said that the people of Meath deserved an
explanation for why that happened. He said the advertisements allowed for submissions
to be made up to 26 January 2002, but that reports had been prepared on 30 and 31
January for circulation to Councillors on the Friday, 1 February, to vote on the Variation
at their meeting on Monday, 4 February.
Mr. Casey said there was a curious matter relating to those variations of the Meath CDP
of 2001 and the Navan Environs Plan of 1997 and he referred to Mr. Killeen's evidence
that the 1994 CDP and 1997 Navan Envirions Plans were important documents to be
considered regarding their objectives together with the 2001 CDP and the Variations as
being the cause of some curiosity for him. He said that he could not see what relevance
was the 1994 CDP now and could not understand what the Navan Environs Plan had to
do with it after the adoption of the new CDP in March 2002 but that he now realised that
the Navan Environs Plan of 1997 was produced as an Area Plan by the Council under the
1963 legislation as part of the infrastructure of the 1994 CDP. He said that when the 2001
CDP kicked in, then everything that had to do with the 1994 CDP was cut off and that
you started with a new fresh clean sheet. He said that he could find no reference in the
2001 CDP of a carryover into that Plan of the Navan Environs Plan of 1997 and said that
if anyone could point him to the carryover into that Plan, he would be delighted.
Mr. Casey then said he would theorise that if there was not a carryover into the 2001
Plan, that there was then a significant and material lacuna in Part 2 of the 2001 CDP
where there was no mention of Navan and its Environs in relation to various County
plans around the County contained in that document. He suggested that at this stage the
lacuna was so gaping that it undermined the viability of the 2001 CDP and said that, at
any rate, the variation proposed to the Navan Environs Plan 1997 on 19 December 2001
was adopted on 4 February 2002. He said that Variation allowed specifically for the
development of a motorway from South Navan up to beyond Ardbraccan and allowed for
the construction of feeder roads from the centre of Navan out in a southerly and
southwesterly direction to the Athboy Interchange and that that was what the Navan
Environs Plan allowed for. He said that it seemed to him that you could not vary a Plan
880
that did not exist and that he was submitting to An Bord that it was highly questionable as
to whether there was any variation of the Navan Environs Plan of 1997 on 4 February
2002, because he was saying no such Plan existed which left a gaping hole in the middle
of the 2001 Meath County Development Plan, and said he was signaling this to everyone.
Mr. Casey then referred to the Consultation processes and to the case of Attorney General
and the relation of Frank McGarry, Paddy O'Hara, Patricia Mulligan,Niamh Crimin, John
Hamilton in their own right re Sligo County Council, Supreme Court 1985, no.118/133,
Walsh, Hedderman,and McCarthy J.J. of 17 February 1989 commonly known as the
Carrowmore Graves case and he quoted from the judgement which, he said, was well
known to An Bord. One part of the extracts he quoted reads " The Plan is the statement
of objectives. It informs the community in its draft form of the intended objectives and
affords the community the opportunity of inspection, criticism and, if thought proper,
objection. --- The private citizen refused permission on such grounds ( ie material
contravention of the CDP) based upon such objectives may consloe himself that it will be
the same for others during the currency of the plan and that the Council will not shirk
from enforcing those objectives on itself."
He said the EPR was adopted by the Councillors on 8 May 2000 with the CDP not
adopted until the following March and asked why, given Mr. Justice McCarthy's words,
the citizens of Meath and his Client, were not given an opportunity to ascertain
essentially what was now adopted by the variation to the Development Plan 8.5 months
after that EPR came into being, which allowed for the motorway to go past Ardbraccan,
and why that was never in the consultation process and the drafts of the Plan prior to its
adoption. Mr. Casey said he would put on the record that the variations were adopted on
4 February 2002 and that the newspaper advertisement of the fact of the variation to the
Meath CDP and Navan Environs Plan was dated 29 May 2002, almost four months later.
He said he could find no explanation why there was such an extendcd period of time
between the adoption of the variation, which took effect immediately, and the notification
to the people of Meath that it had come into being. He said that in April and May 2002
Ms Maher had sent two people to the Council Office in Navan seeking an up-to-date
version of the CDP and that the professional representative was given Volumes 1, 2 and 3
of the 2001 Plan without the Variation and the person who went in on her behalf from
Ardbraccan was given the same. He said that again on instructions a representative of Ms
Maher was sent into the Navan Offices of the Council during the course of this Hearing
in August looking for the current version of the CDP and was again given Volumes 1, 2
and 3 without the Variation.
Mr. Casey submitted that if the chronology he had given was correct, then there had been
a denial of the rights to participate in the process of (a) the routing and positioning of the
road, (b) the CDP, (c) the variation because the variations were published long after the
time had elapsed in which the public and those affected by CPO notices could make their
submissions and objections to the EIS and CPO as the documentation was not available.
He submitted that you could not make a reasoned submission which would be technically
correct in law or in fact unless you were in receipt of, and aware of, the passing of the
variations of 4 February 2002. He said that, to him, amounted to a denial of public rights
881
of participation in the process leading to the Oral Hearing and on to An Bord and any
adoption by An Bord of this scheme.
Mr. Casey said he now wanted to come to the scheme itself and said that the statutory
basis for there being a Hearing was to look at and have an Oral hearing into the CPO and
to participate inn a fact-gathering exercise in connection with the EIS and the EIA. He
said he wanted to remind An Bord that the concept of EIS and EIA was not a creature of
Irish domestic law but was a creature of Europe by reason of the various votes in favour
of further European integration over the years. He said that the Directives relating to EIA,
Habitats and Ecology, Water Quality and Air Quality emanated from Europe and were
binding on us here. He said that we were sometimes good at transposing the requirements
of European Law particularly in the areas of agriculture and such matters, and were
particularly strict in their enforcement, and said that we were not so good in other areas
and were not very good at it in terms of the area of EIA.
He said that some questioning had arisen the previous day relating to data and whether
there was a requirement to furnish data or not as part of an EIS. He said the relevant
directives were 85/337/EC as amended by 97/11/EC on the assessment of certain public
and private projects in the environment. He said the recent Directive updated the original
EIA legislation and amended a number of articles of the 1985 Directive. He read Articles
3 and 5 sections (1), (2) and (3), with section (3) saying in part "The information to be
provided by the developer in accordance with paragraph (1) shall include at least : ---- (3)
the data required to identify and assess the main effects which the project is likely to have
on the environment" and he said that he emphasised that section (3) required the data to
identify and assess the main effects, not the adverse effects but the main effects. He read
the next section as " An outline of the main alternatives studied by the developer and an
indication of the main reasons for his choice taking into account the environmental
effects" and the last section as " A non-technical summary of the information mentioned
in the previous sections". Mr. Casey said he was tendering this to An Bord for
consideration in the context of the EIS before the Hearing for consideration.
Mr. Casey said that the 1997 EIA Amendment Directive was implemented into Irish law
by the 1999 EIA Regulations and that in Schedule 6 it set out the information to be
contained in an EIS and that it mirrored the amendments in the 1997 Directive which he
had referred to above. He quoted the equivalent passage from the 1999 EIA Regulations
and said this included for the inter-reaction between all of those matters including water,
culture and heritage, landscape, soil, air, material assets, flora, fauna, human beings,
climate. He said that if he took the EIS that had been furnished to the public and assumed
that was the only information available to them, until documentation started coming out
of the Council during the Hearing, he would submit to An Bord, who had already allowed
the Hearing to go to Oral Hearing, that if An Bord considered the contents of the EIS
furnished to the Hearing and made available to the public they could not possibly come to
the conclusion that the EIS and the information contained therein complied with the
requirements of either the 1997 EU Directive or those of the 1999 Regulations
implementing that Directive.
882
He said he would give one example of this and said that Ms Joyce might have been
wondering why he had been asking her questions about the conclusions set out in the EIS
at Volume 5A relating to soil, water, geology and hydrogeology and why he was harking
on about the Report of April 2002 which post-dated the EIS and which appeared to
review the question of water, geology and hydrogeology at the Ardbraccan area. He said
that he was not present for the balance of the Hearing on the other Sections all the way
from Clonee but, he said, all the borehole logs, trial pit logs and core hole logs and results
and all the data relating thereto should have been included with the EIS, so that the main
effects of the project on the environment could be identified. He said he had sight of the
borehole test results, Mr. Finlay had a quick glance at them, Ms Maher had the
opportunity of examining them and so had Mr. Sweetman but that no other person
affected by the line of the project from the Durhamstown Road Overbridge to the start of
the Navan By-pass section had been given any opportunity to examine the data referred
to or contained in those Reports. He said that it appeared to him that those borehole logs
were nowhere to be found and that it appeared to him to be a gaping hole in the middle of
the EIS. He submitted to An Bord that it rendered the EIS unacceptable and unworthy of
description with the term of EIS.
Mr. Casey said that Ms Joyce had said that the part on hydrogeology and geology and
other related matters in the EIS were an assessment by someone who was no longer with
the Company and that it was conclusions drawn by him from data that were put in the
EIS and that people were simply supposed to accept a conclusion that he had come to as a
fact. He said that they could not do that, and said that any conclusions posited along the
entire route that were not backed up by the data could not be regarded as sufficient
statements of fact to be assessed so as to (a) identify and then (b) to assess the main
effects on the environment, and then to go on to consider whether they had any adverse
impacts on the environment.
Mr. Casey said that Ireland had a peculiar record with Europe in its track record on EIA
and that Ireland had a peculiar record before the European Commission and before the
European Courts of Justice and was being regularly hauled before the Commission and
the Courts of Justice for failure to implement environmental directives and regulations.
He said he would refer An Bord to the judgements of the European Court of Justice
against Ireland in that regard, including one of the Court Fifth Chamber of 21 September
1999 relating to Directive 85/337/EC for Case C/392/96, which related to thresholds and
matters of that nature. He said that Ireland's defence against that action was that it was
pulling up its socks and that it was improving its EIA regulation and domestic legislation
to enable it to apply the 1985 Directive and said that while this was going on, the 1997
Directive was coming into force with the 1999 EIA Regulations. He said that contrary to
what Ms Dempsey thought, these regulations applied equally to road building projects as
much as they did to any other project and that there was no waiver for road projects. He
said there were no lessor thresholds for roads than there were for dumps, for water
extraction, for airports, for gas terminals or for anything else, with the same rules
applying.
883
Mr. Casey said that in a recent opinion of the Commission addressed to Ireland in, he
thought, September 2001 which An Bord already had from another Hearing, the
Commission, under Article 226 of the Treaty, addressed Ireland's failure to fulfil its
obligations under Directive 85/337/EC and Amending Directive 97/11/EC regarding the
requirements of an EIA and he quoted from page 3 of that Opinion as "The information
to be provided by the developer in accordance with paragraph (1) shall include at least a
description of the project, a description of the measures envisaged in order to avoid ---
the data required to identify and assess the main effects -- etc." He said that the Opinion
dealt with specific cases where the Commission believed that Ireland had been in breach
and that one of those was a road project, complaint P1998/4307, which concerned the
environmental impact of a motorway project in Co. Kildare called the Kildare By-pass
which was given development consent on 22 January 1996 following an EIA. He said
that project involved constructing a motorway below the level of the surrounding land
which required the constant removal of large amounts of water from an acquifer, or a
natural reservoir, to keep the motorway dry and said that everyone present would be
aware of the Pollardstown Fen. He said he was tendering this to An Bord as he thought
that An Bord knew the comments of the Commission in relation to that complaint and he
said that the instigator of that complaint was Mr. Sweetman.
Mr. Casey said that the net effect was that before development consent could be given, all
of the data must be furnished and made available to the public for the public consultation
process and that the public must be consulted and that al of the data in the fact-gathering
exercise would then be assessed by An Bord. He said that it was okay for the EIS to set
out the likely effects on the environment of a particular plan or project, and said that as a
matter of good practice both positive and negative impacts should be set out, and that
then to proceed to come up with whatever the types of remediation or mitigation that
were capable of objective assessment. He said that in the case of this EIS he believed that
it did not contain fact, because the data was not provided, but only the Consultants views
on the merits of this particular project and he said these were saying it was great but we
are not going to give you any of the information which would allow you to question any
of the conclusions reached. He said that Ms Maher had referred to a rather peculiar
statement made to the Hearing which, in effect, said that if it was not put into the EIS
then they could not be blamed for being wrong and he said that the execution of an EIS
with such an attitude did not comply with the legal regulatory framework.
Mr. Casey again referred to the adoption by the Council on 8 May 2000 of the motorway
route and said that was done on the basis of a matrix that was simplified so that they
could understand it and that the effect of that simplification was to merge the boundaries
between the weighted criteria across a number of areas. He said that the crossexamination
had borne that out and that it had been their intention to analyse the matrix
in Table 4.3 and to try and draw a fresh matrix which would be accurate but said that the
ESB power cut had prevented them from doing this. He said that if the matrix presented
to the Councillors for the EPR on 8 May 2000 was examined, there were a number of
areas where the rankings did not make sense and that he would refer to the evidence for
this and would analyse Table 4.3.
884
Mr. Casey then said that when looking at Table 4.3, the summary matrix of the Navan
By-pass in Volume 2 of the EIS and at Routes A to H, it had to be remembered that at 8
May 2000 the 1997 EIA Directive and the 1999 Regulations were in force. He said that
for "landscape and visual" every route was ranked as neutral which he concluded meant
no impact at all and said that seemed strange since Route B went straight through the
front garden, a wing of the House and the stables and trees at Ardbraccan and on towards
the Durhamstown section and the toll plaza. He said that if Route A, which was the Route
now being examined in more detail than the others, was looked at it also said hat
"landscape and visual" was neutral and he asked that An Bord when looking at these two
matters would exercise common sense in seeing if there was any reality to those two
weightings. He said that in terms of "air quality" there was a major negative impact
found for Route A and a moderate negative impact for Route B and wondered how that
difference could have arisen. He said that in terms of "planning and development" the
matrix said Route A was extremely positive and wondered how that could be given the
CDP of 1994 and Navan Environs Plan of 1997 on 8 May 2000. He said that may well be
so in terms of the varied Plan and he suggested it flew in the face of logic that there was a
big blue blob there and that Route B was a major positive since that went through
Ardbraccan House itself. He said he was only analysing Routes A and B at that time to
show how ridiculous that summary matrix was and said that if geology was looked at,
which was neutral across the board, you could not even come to a conclusion whether it
was correct or not on the basis of all that they had heard and been given.
Mr. Casey said that there were a number of items in the Powerpoint presentation to the
Councillors on 8 May 2000 relating to Routes A , B and even H that beggared belief in
logic and he said they would be submitting that to An Bord later on when the ESB was
back on line for them to complete their fresh analysis. He then referred to the Conor
Newman response to Margaret Gowan's written response which had been submitted to
the Hearing by FAX that morning ( See Section 82.2 of this Report) and he read Mr.
Newman's response to Ms Gowan's point 6. He said that it appeared Mr. Newman was
making the point that the favoured route from the archaeologist in the Constraints Report
of February/March 2000 was to go from north of the Hill of Skreen and not to turn
northwest between Skreen and Tara and head to south Navan via Dalgan Park and head
for Ardbraccan south and west of Navan. He said that would mirror the experience of
Valerie J.Keeley in their recommendations of February 2000 when they said if they had
to choose a preferred route, they would say that a route east of Navan and around the
north of the town and to Kells would be the preferred route.
He said that he could not find any reasoning that would upset that viewpoint between
February and May of 2000 because Mr. Breen in cross-examination admitted that the
field walking was only for Route A and was only commenced after 8 May 2000. He said
that Mr. Breen had been forthcoming and fair and that some of the things he had said
might be unpalatable when viewed by the NRA because of he confirming he only started
walking routes after May 2000 and then only route A. He referred to Mr. Breen's
statement that some site excavation including topsoil stripping might be required in the
area to the southwest of the Mound, south of the Bohermeen Overbridge and the corner
of the field that was being landlocked. He said that area was also referred to in Ms
885
Rooney's Report they had tendered to An Bord and said that in the NRA Guidelines of
1999, which were non-statutory but nonetheless binding, it was stated that it would be in
order to conduct trial digs and matters of that sort. He said that in the document issued by
the Department of Arts, Heritage, Gaeltacht and the Islands issued in 1999, "Framework
and Principles for the protection of the Archaeology Heritage" it stated at paragraph 3.6.6
on page 27 that " EIA should, unless there is substantial grounds to show that it is not
necessary, involve the carrying out of archaeology assessment including, where
appropriate, test excavation". Mr. Casey said they knew from Mr. Breen that there would
have to be test excavation along the line of the route passing Ardbraccan and he said that,
not having been present for all of the other areas from Clonee to Kells, he could not say
whether similar excavations should have been carried out elsewhere as part of the EIS
process leading to the data to be contained in the EIS. He said there was nothing to have
prevented this and that it was recommended by Arts, Heritage, Gaeltacht and the Islands.
He said that it left them in an "Alice in Wonderland" situation in relation to how the
various matrices were arrived at for archaeology at Table 4.3 in Volume 2 of the EIS, and
in the matrix presented to the Councillors.
Mr. Casey referred to Ardbraccan itself and said that Mr. O'Sullivan, who had only
become involved long after the route had been adopted by the Councillors, did not really
disagree with all that they, and Mr. Shaffrey, were saying about Ardbraccan. He said that
while there might be slight differences in emphasis, both Mr. O'Sullivan and Mr. Breen
agreed that Ardbraccan was a very rich area in terms of its historical, archaeological,
architectural and landscape context. Mr. Casey said that he had already read into the
record the definition from the 1999 Act relating to national monuments and that
architectural heritage included the historical, cultural, social, archaeological aspects and
the setting and it included groups of sites which, by definition, must include the groups of
sites plus their settings. He said he would remind An Bord that that legislation of 1999
was in force in 2000 and that if any element of common sense was applied in looking at
the setting and the objectives of the CDP, then the placing of a motorway on the
landscape 650 metres away from Ardbraccan directly in its view, within its historical
demesne, that part of it which was no longer in the ownership of the present owners of
Ardbraccan who, at great personal expense, had managed to reclaim that area west of the
farm road, was something which in saying there would not be an effect on the setting by
the imposition of a 21st century superhighway was a ludicrous statement. He said the
Inspector had commented on he taking a quick trip around West Cork to give examples
of the juxtaposition of ridiculous edifices in the settings of some of our more important
historical and archaeological and architectural sites but he had done that to make people
think about what was being imposed on the landscape of Ireland and on those parts of the
landscape which were precious and immoveable and once destroyed could never br
restored.
He then read from Volume 5C at page 16, paragraph 7.3 in Appendix I where Mr.
O'Sullivan referred to the issues raised by Ms. Maher in her letter under four headings
and the letter from Mr. Starret CEO of the Heritage Council to Mr. Tobin CEO of the
NRA and then he read from paragraph 7.4 on page 17 where Mr. O'Sullivan referred to
matters not impinging on the House but on its settings and said that Mr. O'Sullivan was
886
saying it would affect the settings. Mr. Casey submitted that it was a matter of law and
fact that the siting of the motorway with all of its intended environmental impacts,
including traffic, air, noise, water, visual impact, dust, pollution, and whatever affronted
the eye in having to look at it in the context of a richly endowed historic landscape
offended the law, offended the particularity of the objectives of the Meath CDP as
opposed to the general objectives. He said that particular objectives must be given greater
weight than general objectives since they had been made particular. He said the siting
offended against the sense of pride in our surroundings, in our countryside and in our
heritage whether that heritage came from pre-Christian, Christian or Norman times, from
the Protestant Reformation, the 800 year war with Britain or 100 years ago, it did not
matter as it was part of our heritage.
Mr. Casey said that he understood Ms Joyce to say that the Durhamstown road had been
moved off-line further north to facilitate Ms Maher at her request but he took from her
responses to the Inspector's questioning about overpasses being built off-line or on-line
that there was a general policy for overbridges to be built off-line because of mounding
and houses along the line. He said that if that was the case then it seemed to him the
present positioning of the Durhamstown Overbridge was in line with the general policy
of the NRA as opposed to being put there to accommodate the wishes of Ms Maher.
He said that he understood Mr. Searson had given evidence and had been cross-examined
about noise and that the outcome was that noise would present an adverse significant
impact on the House and settings of Ardbraccan and said that would escape onto the uses
of Ardbraccan in terms of noise pollution. He said that there was nothing in the EIS, or
before the Hearing, to suggest that the interactions between the noise and the uses of
Ardbraccan and its demesne were tested or that the interaction between noise and air
pollution, Ardbraccan, its landscape, its setting, its cultural heritage, its archaeology, its
water, effects on water, geology, hydrogeology or its landscape were considered in their
inter-relationships to one another in accordance with the EIA directive and the Irish
Regulations.
Mr. Casey said that the problem was that Ms Maher and her husband, who had lavished
time and money on the restoration and conservation of Ardbraccan, could not even deal
with the NRA and Council on the question of a deep cutting of the roadway to ameliorate
noise because the underlying ground conditions were not known. He said that it appeared
there was overburden of some nine metres from the borehole results for Durhamstown
and possibly further back the route for maybe 200 yards to the south where there
appeared to be four more boreholes near the location for the possible borrow pits. He said
that in the absence of any data or analysis of data relating to ground water, geology and
hydrogeology, it was not possible to assess whether it was possible to cut down into this
nine metres of overburden to try and remedy the noise, air pollution, visual impact and
visual intrusion on the landscape context and setting of Ardbraccan.
Mr. Casey said that even if they had tried over the last three years to deal with the
Council and the NRA and their various advisors, they would have had to try and amass
all of the data themselves to make an assessment of all the interaction between all of
887
those matters. He said they could not have come to any conclusive view with the Council
since the Council simply had not given any of the data or looked at any of those
interrelations not alone for Ardbraccan but, he said, that nowhere in the totality of the EIS
for the motorway were those inter-relationships taken into account as required by law.
Mr. Casey said that in relation to the Durhamstown Road Overbridge they did not know
whether it could be put seven metres into cut, when it could have been up to 1.9 metres
above ground with the Durhamstown Road overpass underneath, 10 metres from the
surface of the motorway.
He said they did not know if a large mound, like that described by Ms Maher at her
family home in Buckinghamshire, could be put between the road and the House as
nobody had ever addressed that question. He said nobody had addressed the question of
looking west from Ardbraccan House along the route of the motorway between
Bohermeen Road Overbridge and Durhamstown road of whether mounding could be
done or if a deep cut could be put there, and he said that by deep he meant 7 to 10 metres
and not 3 or 4 metres, as an amelioration of the significant adverse impacts on
Ardbraccan.
He said that there had been various promises made during the Hearing relating to
lighting, screening and planting of trees and he referred to Mr. Evans comments about the
point where the tangential light started towards Ardbraccan. He said he understood that
was on an embankment and as his calculations showed this to be about 1 or 2 metres
above the surrounding ground, then it would require 10 metre trees to raise the trees to a
height of 8 metres over the roadway. He doubted the feasibility of a timber screening
along the side of the road there to try and divert the flash of headlights and said these
were matters that could not be dealt with since the people who were responsible for doing
so, ie the promotors of the project, never addressed it at all.
He said that Mr. Burns had told the Hearing, by reference to a photograph taken from the
Bohermeen Road looking north along the stonewall which incorporated tree screening
and the gate pillars, that these would have to be retained and he said that Mr. Burns had
indicated, even if not in formal words, that in the event of development consent being
given that 10 to 12 to 15 metres from the western edge of that wall boundary to the top of
the embankment leading down into the cutting would be planted and that was in the
nature of an undertaking. He said that the engineering drawings indicated that would
involve taking land from the eastern side of that wall which was not allowed for in the
CPO maps. Mr. Casey said that it appeared to him from these drawings that if screening
of 12 metres was to be kept the whole way up to Durhamstown, that it could not possible
be done within the landtake and also have two in one embankments, drains 1 to 1.5
metres, the median strip and the minimum carriageways as set out in Volume 2 of the
EIS. He suggested that the Inspector should "run his ruler" along that area from
Bohermeen to Durhamstown and do the same exercise as he had done. He suggested that
the Inspector would also conclude that the screening mitigation proposed for that section
could not be achieved within the landtake and also allow for the minimum design
requirements of Volume 2 relating to carriageways etc. He said that from his examination
it appeared as if the landtake from a point some distance to the north of Bohermeen
888
Overbridge, possibly after a few hundred yards, was 16 metres too little in terms of its
width and that shortfall continued for some distance northwards. He said that even if the
mounding to ameliorate noise as outlined by Mr. Searson was started at that point, the
bunding would require a greater landtake and said that unless that was taken from Ms.
Maher he could not see how the NRA, or the concessionaire, could possibly comply with
the kind of undertakings being suggested by Mr. Burns the other day.
Mr. Casey said there was an issue about the Farm Road and that the Inspector had invited
him to make a submission about this. He then submitted that if a dual carriageway was
being given sanction in this area, then the Farm Road should be closed off from the
Durhamstown road right down to the Five cross roads other tan for the people who lived
along the road and the people who owned Ardbraccan or, effectively, the landowners.
He said he had one final matter he wanted to refer to and that was about the public
questionaires handed out as the choice of questions used always puzzled him. He said
what puzzled him even more was the weighting given to various answers as they had
been told that 79% of people said that proximity to the motorway would be their biggest
issue. He said that the answer of "people living near the route 79%" to " what in your
opinion is the most important consideration" might be an Ibsenism but whether it was
that the people living near the route should be accommodated to allow then gain access to
the route or as in the people living in east or north of Navan. He said the second most
important weighting to" what in your opinion was the most important consideration" was
that 71% said archaeology and historical sites. He said that was part of Ms Joyce's
Powerpoint presentation to the Councillors on 8 May 2000 and that if indeed archaeology
and historical sites were so important to the people who filled in their questionaires and if
found to be an important consideration to put before the Councillors in terms of
weighting, then why was not more thought and more consideration given to it.
Mr. Casey concluded his submission by saying he would return to the Carrowmore
Graves judgement and that he wanted to quote from the final paragraph where Mr. Justice
McCarthy said " I would not like to end this judgement without paying tribute to the
courage of those who have at considerable monetary risk challenged the conduct of the
Local Authority in County Sligo, thereby going some way to answer the stated
observation of important archaeologists in the western world " Do the Irish have no
pride" ".
143. 6. Closing Submission by Peter Sweetman, on behalf of An Taisce :
Mr. Sweetman said that he would deal with the trees in Ardbraccan at the start of his
submission and said that one of the Beech trees in Ardbraccan had honey fungus which,
when it came into an estate, might stay dormant for a while or it might run rampant
throughout the estate. He said that no-one knew why it decided to do that but if it did
decide to run rampant, every tree around Ardbraccan House would die and that any
mitigation measures based on the survival of those trees were ill-founded. He said that
the Copper Beech, which was the most important screen at the back of the house, had
bracket-fungus and was at the end of its life and had to be assessed whether to take it
889
down now or wait for next year. He said that the small Beech in the middle of the view
had a forked leader at about 15 feet and would not grow into a substantial tree and that
the large Beech on the left as you looked from the house was mature to over mature and
might fall in the next storm. He said that if it happened that those three trees went, the
entire house and the view, which was the view used for the light in the photograph,
would then be exposed to the road from the toll plaza.
Mr. Sweetman said that the Ash trees at Durhamstown were overgrown hedgelings and
were growing on a bank, were inadequately supported and would be extremely prone to
constructionitis and he said that they had now discovered that movements of the
watertable were certain to take place on that site and said the trees could not be relied on
for any manner of screening. He said these trees also appeared to have a certain amount
of cavities in them and that Ash trees with cavities were the normal habitat of Bats. He
said that Mr. Burns was relying of the trees already in the landscape to mitigate the
impact on the landscape without doing any survey.
Mr. Sweetman said that they had heard on numerous occasions how the Council had
deliberately set out to obstruct throughout this development. He said that when Mr.
Keane could magically produce documents off the Material Contravention File which
were not on it 12 hours previously and refused to answer where he got it from or whose
possession it was in was an example of this obstruction. He suggested that Mr. Keane's
reason for refusing to answer was because the document had been deliberately suppressed
from the public. He said that the Council had worked on a need to know basis all the way
through and that this was abusing the public as it was a fundamental requirement of the
EIA process that the public be consulted. He said that Fr. Pat Raleigh had given similar
evidence of abuse by the Council to that of Ms Maher and he said that there had been
others who had also complained.
He said that An Taisce believed that some route improvement was required from Clonee
to Dunshaughlin and that Dunshaughlin needed to be by-passed and they accepted that
Navan needed some relief. He said that he had been going to say that An Taisce saw
nothing wrong with the Clonee to Dunshaughlin section and said that he really had not
looked at that section. He said that in view of the incompetence and deception in the
other sections they had looked at from Dunshaughlin to Navan and the Navan By-pass,
he could not recommend to even accept that part of the road since he saw no reason why
it should have been more competently looked at than the sections they had looked at in
detail.
Mr.Sweetman said it was absolutely clear from the evidence put before the Hearing that
the wrong route was chosen for that the Dunshaughlin to Navan section. He said the
Council continually relied on the socio-economic survey by someone who knew
absolutely nothing about socio-economics. He said that everything pointed to the Navan
By-pass going east of Navan and that the only reason for not putting it east of Navan
appeared to be that there was some clay east of a tailings pond that might be used to build
a tailings pond extension at a future time. He said that clay to build this tailings pond
could be sourced anywhere in Meath as Meath was basically deep clay soil. He said that
890
it was not a reason to destroy our heritage because the Navan mines might or might not
want to extend the tailings pond. He said he was one of the objectors to the tailings pond
and that it turned out that everyone was happy and that the conditions were basically
agreed and greatly improved the process. He said that it was a consultation process with
Tara Mines rather than a confrontation process with everything put on the table. He said
that the grass grew on one half of the tailings pond because they had spread mushroom
compost on it and planted grass and that while there was an element of cadmium
pollution there at two parts per million, the tailings pond was absolutely safe and without
any substantiation from the Council.
Mr. Sweetman said that the route selection of these two sections was fundamentally
flawed and that if the route selection from Dunshaughlin to Navan had been done
properly and proper alternatives looked at, it would have been impossible for it to come
out with the route that they now had come out with. He said that he and An Taisce
supported everything that Mr. Casey had said about the EIS, and he was just going to
extend that to the rest of the route. He said that the EIS was fundamentally flawed in law,
that it did not comply with th 1999 Regulations and did not comply with the NRA's own
road design guidelines.
He said that Ms Dempsey had said on Day one or two that the 1999 Regulations did not
apply to road designs and said he wanted to draw attention to the NRA's Project
Guidelines at page 38 and chapter 4. 3.1where the particular topic outlined were the EC
EIA Regulations SI 93 of 1999. He said one of these was archaeology and the NRA
version said that archaeology should include the necessary exploratory investigations. He
said that Ms Dempsey, Ms Gowen and Ms Joyce all said they did not do it that way but
did it afterwards. He said that was what happened at Carrickmines and was why the
Commissioner wrote once again to the Irish Government for not complying with the EIA
Directive. He said permission was given to a road without assessing the ground water and
massive problems arose and that the Glen of the Downs suddenly became an SAC and
this had not been looked at. He said that roads were no different to any other
infrastructure and were in the First and Second schedules requiring full EIA. He said that
this was also stated in the NRA guidelines which Mr. Whyatt said were in draft and said
that there were previous guidelines, version 1.0 of May 1999 which said much the same
thing including the 1999 Regulations, and there was no mention of draft on version 1.1 of
March 2000. He said this was another case where the Engineers in this project said they
knew best and did not need rules, they did not need to tell the public and did not need to
consult as they knew best and would talk down at people.
He said that the assessment of the ecology at the Boyne Valley crossing was non-existent
and that the same document said that where you were crossing an SAC detailed
mitigation measures should be put in place. He said that the "fumbled" mitigation
measures proposed at the site did not actually fit into the site relevant to the construction,
so they could not be implemented. He said that the EIS contained no details of the source
of the raw materials or of the deposition of waste and that the interactions of these was
something that was considered in the EIS and that nobody could answer questions on it at
the Hearing because everybody was passing the buck. He said that the micro-climate
891
relative to the road was not considered and there were fog patches in places and the
relevance of the Tara Mines shaft was not considered but that the mud for the tailings
pond was considered as very important. He said that there was no data for ground water
and that construction traffic was averaged over the entire route. He asked what was the
construction traffic at Ardbraccan and said nobody knew because no-one assessed it and
it was not in the EIS. He said that they said something would be done about it but that it
never was unless it was pinned down and that it could not be said what the mitigation
measures were on any point on the road because they were not in the EIS.
Mr. Sweetman said that he had to repeat what Ms Dempsey had said at the very
beginning which was that they did not put things in the EIS which they did not think were
necessary because if it was not in the EIS they could not be questioned on it and he said
that was very arrogant, but said that it might not be the exact wording but was something
on those lines and that the Inspector would read it for himself in the transcript. He said
that the information contained in the EIS relevant to the toll plazas was not, as he had
said previously and would say again, adequate to build a one-room cottage with the
information supplied and not adequate for a toll plaza. He said that he was convinced that
the 2001 Development Plan was a document that deliberately set out to deceive trhe
public and no evidence had been produced to convince him of anything else. He said they
had heard no mention of the White Quarry or Ardbraccan Quarry which was a late 17th or
early 18th century quarry out of which the stone came for some of the most important
buildings in this country such as Leinster House, Carton, the Customs House and
Ardsallagh. He said that the White Quarry had been flooded and filled in for many years
and that a cursory glance at the aerial photograph would have told the Engineering Team
that they had serious groundwater problems in that area because of its high watertable.
He said there had been evidence of PM10s and that the baseline levels of PM10s
presented was below the naturally occurring level so that they were not going to appear to
high when the evidence came in. He said that the noise data which had been collected on
the site was going to be ignored because the Engineering Team decided it did not fulfil
the criteria they had set themselves. He said the object of an EIS and assessment was that
all the relevant data be presented by the developer and that where the developer refused
to produce relevant witnesses, then it could only be stated that the relevant data was
either highly suspect or the developer was embarrassed at what might the answers might
be. Mr. Sweetman said that the no-show by Duchas at the Hearing on both ecology and
natural environment showed the sorry state this country was in relevant to its
implementation of the Habitats Directive. He said he welcomed the fact, and hoped it
would be soon, that the European Commissioner would be sending a European civil
servant to run Duchas because they were incapable of running it themselves.
Mr. Sweetman said that Mr. Perkins had his name on every document presented at the
Hearing but was nowhere to be seen as he was embarrassed at what had been put forward
and that so he should have been. He said that Mr. Murphy, who really was a developer,
was hiding under some stone because he was perpetuating a con-trick in planning terms
since this was a development by a private company looking to transfer an exemption
from the Planning Authority, and said that he did not want to tell the Hearing that
892
because he was embarrassed by it. He said that point 9 of Mr. Newman's submission
clearly stated what Mr. Lumley was trying to point out to Mr. Keane, while Mr. Keane
was being aggressive to him. He said that no-one looked at the electricity line that
crossed the Deer Park ( at Ardbraccan) and how it would cross the road and he would
love to have known.
Mr. Sweetman concluded his submission by saying that he hoped and was confident that
this road project would be the second road project in the country that would be refused
permission because it was outrageous.
145. 7. Closing Submission by Pat Butler S.C. for the Council :
Mr. Butler said that the exercise commenced on 21 August and now concluding on 21
November was, as had been restated several times, a fact finding exercise to give An
Bord all of the relevant information to allow them to make an assessment of the
environmental impacts of the development and to decide whether the scheme should go
forward. He said that his comments would only deal with facts insofar as they were
relevant to illustrate the legal issues raised by the objectors and that he would leave it to
the Inspector to balance the arguments made throughout the period of the Hearing. He
said there were two issues that he wanted to deal with at the end of his submission and
these were the route selection issue, which had been raised by various parties, and the
relationship between the Council as Road Authority and the promoters of the scheme and
the NRA.
He said that he would deal with the issues in the order they had been raised and,
commencing with the EIS, he said that Section 50 of the 1993 Roads Act as amended by
the 1999 Regulations set out what was required in an EIS and that Section 50 started off
by saying that an EIS must be prepared by a road authority for the types of development
set out in Section 50, including a motorway, in respect of the likely effects of the
proposed road development. He said that was absolutely critical in dealing with many of
the criticisms made by the objectors since it had been constantly stated and put to
witnesses appearing for the Council that what they were doing was justifying something
that they had already decided on. He said that it had frequently been explained to the
objectors that the Act specifically said that a project, the proposed road development,
must exist before the EIS was done and that therefore the EIS must by its nature and in
accordance with law deal with that road project. He said that the EIS must also look at the
alternatives that were considered but that it was not an EIS of these alternatives. Mr.
Butler said that that was the fundamental error many of the objectors had been making
throughout the Hearing when they had constantly asserted that what a proposer of a
scheme like this should do was not alone an EIS relating to the project, but one for every
alternative and he said that was not what was required.
He said that there must be a proposed road development and it was the likely significant
effects of that development that were to be considered. He said that the evidence that had
been put before the Hearing, throughout its entire length, had displayed that the likely
893
significant effects had been inquired into and that the required mitigation measures had
been set out and he submitted that was the position. He said that in the end it was still a
matter for An Bord to decide.
Mr. Butler said that much time had been spent putting the Project Engineers, and some of
the other witnesses for the Council, through extensive cross-examination relating to
matters which had led up to the decision to carry out this development and to propose the
scheme. He said they were undoubtedly entitled to go back and look at the Constraints
and other studies that had been carried out but that once the project was decided on then
it was that project which was the subject of the EIS. He said that brought up again the
proposition that the EIS was prepared to justify a proposal and insofar as that proposition
had been made, he said that he rejected it and he said that it was quite clear from the
legislation that this could not possibly be the basis on which the EIS was prepared.
Mr. Butler said that Mr. Casey in his submission had echoed some of the criticisms made
throughout the Hearing by various bodies or objectors but not to the same extent as those
made by Mr. Sweetman. He said that Mr. Sweetman seemed to have a paranoid view of
anything carried out by a public body and saw conspiracy at every turn. He said that there
had definitely a view taken by some objectors over the period of the Hearing that, in
some way, the Council had been hiding documents and had not been open. He said he
wanted to reject that view and said that it was quite clear, whatever the perception of
objectors, from listening to each of the witnesses for the Council that every attempt had
been made on their part to be open and explain and to be helpful.
He said that there had been criticism of the EIS as to its content and clarity in its function
of informing the public and said that it was interesting to note that a number of
professional witnesses appearing for objectors had invariably praised the EIS. He referred
to Mr. Conor Newman's first submission where he had stated that " Indeed the carc that
has gone into the preparation of this section of the various EIS statement is itself a
reflection of the standing of Tara." He referred to Mr. Terence Reeves Smyth's report for
Ms Maher which said " I have now read through Dr. O'Sullivan's contribution to the EIS
and feel that on the whole his report is quite good. Indeed it is superior to many other EIS
reports I have seen." He said that Mr. Peadar Creagh had made a presentation on behalf
of Raynestown when he said " The EIS is very well put together, it is hard to find fault
with it." He said those were examples where an objective view had been taken of the EIS
which found it to be a comprehensive, detailed and efficient report. He said that it was
also notable when Mr. Sean Finlay was called as a witness for Ms Maher and was asked
about the EIS that he did not say that any significant effect had not been set out in
relation to the geology, and that he had not criticised the EIS nor was a suggestion of a
criticism put to him.
Mr. Butler said that the issue of whether the traffic figures justified a motorway had been
raised at the early part of the Hearing by Mr. Frank Burke on behalf of his clients and he
said that the debate which had ensued on the previous day between Mr. Burke and Mr.
Evans had finally nailed that issue and said that Mr. Evans had made out,
comprehensively, the case for the motorway.
894
He said that the context of the Strategic Policy Guidelines (SPGs) was an issue that
concerned many people in the locality relating to the probable or possible provision of a
rail link from Navan to Dublin and why that was not considered as alternative. He said
that the legislation was quite clear and that the two words used relating to alternatives in
the Regulations were "what alternatives (if any) were considered". He said there was no
requirement to consider an alternative if that alternative had no bearing on the project in
hand and that, in any case, the SPGs themselves said in relation to rail that, until a proper
feasibilty study was carried out regarding the provision of a rail link, it was not an issue.
Mr. Butler submitted that it was quite correct that the alternative of a rail link balanced
against the provision of the motorway was not a proper matter to be taken into account.
He said that, additionally, the SPGs themselves in providing for a strategic transport
corridor clearly included the provision of a motorway and said that word was used in the
SPGs. He said it was clearly envisaged by the SPGs that, whatever about the other type of
transport links, a motor way would be provided.
Mr. Butler said that the issue of public participation had been repeatedly raised and said
that this had to be put in the context of the legislation which, in the case of Section 50,
required the specific publication of certain notices about the making of the scheme, times
for objection etc. He said that there was no requirement in law for what had now
developed as public consultation. He said there was provision in the Directive 85/337/EC
for the competent authority, in this case Ireland, to set out within its own legislation
provision for written submissions, public inquiry and time scales within which that
inquiry took place but said nothing about public consultation. He said that the system
developed in this country had gone further than the requirements, both Statutory and the
Directive, and had put public consultation into being and said that those public
consultation processes were carried out. He said that insofar as an argument was made by
the objectors that the public consultation process was not in accordance with the NRA
guidelines, he submitted that guidelines were guidelines and were not strictures or
statutory requirements. He said the guidelines were a template and an aid to help
individual local authorities to direct their affairs and said that if they diverted from them
this was not an infirmity in law, giving the example where the High Court so held in the
case of Smith and McEvoy v. Meath County Council.
He said that Mr. Sweetman had again raised the issue of the import of materials which
had been raised on a number of occasions in the Hearing and said that he was not going
to go through this in any great detail as the Inspector had heard submissions on that issue
at a very early stage of the Hearing. Mr. Butler said that the 1999 Regulations provided
for the promoter of a given scheme to be able to supplement the information during the
Hearing process and also provided that the information contained in the EIS need only be
such as was required to identify the project at the stage at which the Hearing process had
reached. He submitted that for all of those reasons and the reasons relating to future
processes dealing with planning applications etc, the EIS had adequately identified the
volumes and the effects of the import of materials.
895
He said an issue had been raised of "project splitting" and that issue had been raised in
the context of the reasoned opinion from the EC quoted by Mr. Casey and said that a
fundamental misconception had arisen about that whole concept and was constantly
reiterated by objectors. He said that the reasoned opinion was directing the Irish
Government's attention to particular issues and gave, as an example, the case of the
Ballymun Development Regeneration Scheme where the developer divided that scheme
up into 15 separate applications instead of applying for permission in one project. He said
that the purpose of dividing it was to make each application below the threshold requiring
an EIS and the Commission rightly pointed out that was not within the spirit or letter of
the Directive and should not have been allowed. He said that in the case of the M3
Scheme there were five projects merged into one big scheme and said that how this could
be argued to be project splitting was inconceivable and that, in any case, an EIS had been
prepared whereas the EC was complaining about splitting of projects to avoid preparing
an EIS.
Mr. Butler said that the position of the Elected Members had been raised and raised again
in his submission by Mr. Casey and he said he was surprised at Mr. Casey asserting that
the Elected Members had adopted the scheme, since he should know what their position
was. He said that the Elected Members did not adopt the scheme as the drawing up and
proposing of a scheme was an executive function and that Mr. Casey should know the
distinction between a reserved and an executive function. He said that the drawing up of
the scheme under the 1993 Act was not a reserved function of the Members but that the
County Manager had properly kept them informed of progress with the scheme and that it
had been presented to the members for their views. He said that the Elected Members had
voted for the provision of the County Development Plan 2001which included the
provision of a motorway in accordance with the scheme, as presented, and with a map
attached to the Plan which showed the motorway passing Ardbraccan. He said that the
Elected Members also passed the resolution amending the 2001 Plan and the Navan
Environs Plan specifically to take account of changes that had been made to the route. He
said that even if it could be said that there was some imperfection in the part played by
the Elected Members in bring forward the scheme, it was clear that they knew what was
provided for in the Plan and in the amendment.
He said that the issue relating to the Tree Preservation Order at Dalgan Park had been
raised and said that the Inspector should be satisfied from Mr. Killeen's evidence that the
Tree Preservation Order was provided for in both the 1994 plan and in the 2001 Plan.
Mr. Butler then referred to the argument made on Ms Maher's behalf about the variation
and said that the scheme and the indicative route were set out in the 2001 Plan at Section
3.5.2. (ii) at page 51 and bullet point 3 and provided specifically for a motorway from
Clonee to Kells. He said that Ms Maher had brought proceedings relating to the variation
of that Plan on the basis that she was not informed and did not know that a motorway was
to pass her property when, he said, that was quite clearly stated in the 2001 Plan. He said
that whatever arguments Mr. Casey had made in relation to what he perceived as
infirmities in the way the variation was brought in, that had no bearing on the fact that Ms
Maher and everybody in the Navan area was on notice from the 2001 Plan of March 2001
896
that a motorway was passing in the area as indicated. He said a further issue raised out of
the Plan in Ms Maher's submissions was that a Planning Application was refused in the
Ardbraccan area, with six reasons given, and that because one of those reasons was that
the setting of Ardbraccan would be affected, it had been argued from this that the placing
of the motorway in the setting of Ardbraccan was a breach of the Development Plan. He
said that argument could not have any substance when the provision of the motorway was
a specific objective in the CDP.
He said that Mr. Galligan, Ms Maher's then Counsel, had raised an issue at the start of the
Hearing about the notice published in the newspaper that the variation was about to be
debated and said that Mr. Galligan had argued the that the