Back to INDEX of reports
@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@@
625
PART 4 -- NAVAN BY-PASS, NAVAN TO KELLS, N52 KELLS BY-PASS
AND KELLS TO NORTH OF KELLS SECTIONS
--------------------
NAVAN BY-PASS SECTION
-------------------------------------
86. Evidence of Susan Joyce -- -- -- -- -- -- -- -- -- -- -- 628
86. 1. Examined by Mr. Keane -- -- -- -- -- -- - -- -- 628
86. 2. Cross-examined by Sean Carty -- -- -- -- -- -- - -- 635
86. 3. Cross-examined by Manus Tiernan & Jim McIntyre -- -- - -- 636
86. 4. Cross-examined by Jim McIntyre -- - -- -- -- - -- - 643
86. 5. Cross-examined by Stephen Gunne -- -- -- -- -- -- -- 644
87. Submission by Frank Burke -- -- -- -- -- -- -- -- 645
88. Evidence of Phillip Farrelly -- -- -- -- - -- -- -- -- -- 645
88. 1. Examined by Mr. Keane -- -- -- -- -- -- - -- -- 645
89. Evidence of Chris Dilworth -- -- -- -- -- -- -- -- - 646
89. 1. Examined by Mr. Keane -- -- -- -- -- -- -- -- -- 646
89. 2. Cross-examined by Manus Tiernan & Jim McIntyre -- -- - -- 648
89. 3. Cross-examined by Jim McIntyre -- -- -- -- -- -- 651
90. Evidence of Bill O'Kelly-Lynch -- -- -- -- -- -- -- - 653
90. 1. Examined by Mr. Keane -- -- -- -- -- -- -- 653
91. Evidence of Richard Nairn -- -- -- -- -- -- -- 654
91. 1. Examined by Mr. Keane -- -- -- -- -- -- -- 654
92. Evidence of Jean Clarke -- -- -- -- -- -- -- 657
92. 1. Examined by Mr. Keane -- -- -- -- -- -- -- 657
93. Evidence of Edward Porter -- -- -- -- -- - -- 658
93. 1. Examined by Mr. Keane -- -- -- -- -- -- -- 658
94. Evidence of Bill Quirke -- -- -- -- -- - -- 660
94. 1. Examined by Mr. Keane -- -- -- -- -- -- -- 660
94. 2. Questioned by Inspector -- -- -- -- -- -- -- -- -- 661
95. Evidence of David Wilson -- -- -- -- -- -- -- -- -- 662
95. 1. Examined by Mr. Keane -- -- -- -- -- -- -- -- -- 662
95. 2. Cross-examined by Manus Tiernan & Jim McIntyre -- -- -- 663
96. Evidence of Alan O'Connell -- -- -- -- -- -- -- -- -- 665
96. 1. Examined by Mr. Keane -- -- -- -- -- -- -- -- -- 665
97. Evidence of Harold O'Sullivan -- -- -- -- -- -- -- -- -- 667
97. 1. Examined by Mr. Butler -- -- -- - -- -- -- -- 667
98. Evidence of Thaddeus Breen -- -- -- -- - -- -- -- - 667
98. 1. Examined by Mr. Keane -- -- -- -- -- -- -- - -- 667
99. Evidence of Thomas Burns -- -- -- -- -- -- - -- -- 668
99. 1. Examined by Mr. Keane -- -- -- -- -- - -- -- -- -- 668
100. General Submissions -- -- -- -- -- -- -- -- 672
100. 1. Verbal Submissions -- -- -- -- -- -- -- -- 672
100. 2. Written Submissions -- -- -- -- -- -- -- -- 676
626
101. Council's Responses to Submissions --- -- -- -- -- -- -- 678
NAVAN TO KELLS AND KELLS TO NORTH OF KELLS SECTIONS
--------------------------------------------------------
102. Evidence of Michael Evans -- -- -- -- -- -- - -- -- 680
102. 1. Examined by Mr. Butler -- -- -- -- -- -- -- -- 680
102. 2. Cross-examined by Michael Meegan -- -- -- -- -- - 692
102. 3. Cross-examined by Mr. O'Donnell -- -- -- -- -- 694
102. 4. Cross-examined by Niall Sudway -- -- -- -- - - 697
103. Evidence of Phillip Farrelly -- -- -- -- -- -- -- -- 698
103. 1. Examined by Mr. Butler -- -- -- -- -- -- -- - 698
104. Evidence of Edward Porter -- -- -- -- -- -- -- -- 699
104. 1. Examined by Mr. Keane -- -- -- -- -- -- -- -- 699
105. Evidence of Siobhan Deery -- -- -- -- -- -- -- -- 701
105. 1. Examined by Mr. Butler -- -- -- -- -- -- -- -- 701
105. 2. Cross-examined by Peter Sweetman -- -- -- -- -- - 705
105. 3. Cross-examined by Mr. O'Donell -- -- -- -- -- -- 705
106. Evidence of Jackie Jordan -- -- - -- -- -- -- -- 706
106. 1. Examined by Mr.Butler -- -- -- -- -- -- -- -- 706
106. 2. Cross-examined by Peter Sweetman -- -- -- -- -- -- 710
106. 3. Questioned by Inspector -- -- -- -- -- -- -- -- 712
107. Evidence of Thomas Burns -- -- -- -- -- -- -- -- 712
107. 1. Examined by Mr. Keane -- -- -- -- -- -- -- 712
108. Evidence of Chris Dilworth -- -- -- -- -- -- -- -- 719
108. 1. Examined by Mr. Keane -- -- -- -- -- -- -- -- 719
108A Council's Review of Noise Limits -- -- -- - -- -- -- 721
108. 2. Questioned by Inspector -- -- -- -- -- -- -- -- 724
108. 3. Cross-examined by Frank Burke -- -- -- -- -- -- - 727
108. 4. Further examined by Mr. Keane -- -- -- -- -- -- -- 728
108. 5. Cross-examined by Karl Searson -- -- -- -- -- -- 728
108B Karl Searson questioned by Mr. Keane & Inspector -- -- -- -- 731
108. 6. Cross-examined by Peter Sweetman -- -- -- -- -- -- 731
109. Evidence of Bill O'Kelly-Lynch -- -- -- -- -- -- -- 732
109. 1. Examined byMr. Keane -- -- -- -- -- -- -- 732
109. 2. Cross-examined by Peter Sweetman -- -- -- -- -- -- 733
110. Evidence of Richard Nairn -- -- -- -- -- -- -- 736
110. 1. Examined by Mr. Keane -- -- -- -- -- -- -- 736
110. 2. Cross-examined by Peter Sweetman -- -- -- -- -- -- 749
111. Evidence of Kevin Cleary -- -- -- -- -- -- -- -- 756
111. 1. Examined by Mr. Keane -- -- -- -- -- -- -- -- 756
112. Evidence of Betty Newman Maguire -- -- -- -- -- -- 758
112. 1. Examined by Mr. O'Donnell -- -- -- -- -- -- -- 758
112. 2. Questioned by Mr. Butler -- -- -- -- -- -- -- 759
112. 3. Re-examined by Mr. O'Donnell -- -- -- -- - -- -- 760
113. Evidence of Karl Searson -- -- -- -- -- -- -- -- 760
113. 1. Evidence of Karl Searson for Betty Newman Maguire -- -- -- 760
627
113. 1. 1. Karl Searson cross-examined by Mr. Keane -- -- -- 761
113. 2. Evidence of Karl Searson for Sarah Maher, Ardbracccan House -- - 762
114. Evidence of Ronald Bergin -- -- -- -- -- -- -- -- 764
115. Inspector's questions to Project Engineers -- -- -- -- - 765
116. Documents submitted by Council from Inspector's requests -- -- 768
117. Evidence of Alan Guthrie on Extinguishment of Rights of Way etc. -- 772
117. 1. Examined by Mr. Butler -- -- -- -- -- -- -- 772
118. Submission by Mr. Casey on Boyne Navigation Rights -- -- -- 773
119. General Submissions -- -- -- -- -- -- -- -- 773
118. 1. Written Submissions -- -- -- -- -- -- -- -- 773
120. Council's Responses to Submissions -- -- -- -- -- -- -- 775
ARDBRACCAN HOUSE MODULE
------------------------------------
121. Preliminary Submissions by Mr. Casey -- -- -- -- -- -- 776
121. 1. Evidence of Peter Sweetman -- -- -- -- -- -- -- 779
122. Response by Mr. Butler -- -- -- -- -- -- -- -- 781
123. Response by Mr. Casey -- -- -- -- -- -- -- -- -- 782
124. Ruling by Inspector -- -- - -- -- -- -- -- -- -- 782
125. Peter Sweetman cross-examined by Mr. Keane -- -- -- -- -- 783
126. Exchanges between M/ s Casey and Keane -- -- -- -- -- 784
127. Susan Joyce cross-examined by Mr. Casey -- -- -- -- -- 785
128. Michael Evans cross-examined by Mr.Casey -- -- -- -- -- 789
129. Colin Andrew examined by Mr. Casey -- -- -- -- -- -- 796
129. 1. Colin Andrew cross-examined by Mr. Keane -- -- -- -- -- 798
130. Thaddeus Breen cross-examined by Mr. Casey -- -- -- -- - 799
131. Harold O'Sullivan cross-examined by Mr. Casey -- -- - - -- -- 802
132. 1. Thomas Burns cross-examined by Peter Sweetman -- -- -- - 808
132. 2. Thomas Burns cross-examined by Mr. Casey -- -- -- -- -- 810
133. Video & Powerpoint Presentation by Sarah Maher -- -- -- -- 815
134. Susan Joyce & Michael Evans cross-examined by Mr. Casey -- - -- 819
134. 1. Susan Joyce & Michael Evans cross-examined by Frank Burke -- -- 836
134. 2. Susan Joyce & Michael Evans questioned by Inspector -- -- -- 844
135. Evidence of Frank Burke -- -- - -- -- -- -- -- - -- 844
136. Evidence of Sean Finlay -- -- -- -- -- -- -- -- -- 846
136. 1.Examined by Mr. Casey -- -- -- -- -- -- -- -- 846
136. 2. Questioned by Mr. Keane & Inspector -- -- -- -- -- 848
137. Inspector's comments about remaining Briefs of Evidence -- -- -- 848
138. Evidence of Sarah Maher -- -- -- -- -- -- -- - -- - 849
138. 1. Cross-examined by Mr. Keane -- -- -- - -- -- -- 855
138. 2. Questioned by Inspector -- -- -- -- -- -- -- 856
139. Questions to Council by Inspector -- -- -- -- -- -- -- 856
140. Susan Joyce questioned by Inspector -- -- -- -- -- -- - 857
141. Michael Evans questioned by Inspector -- -- -- -- -- -- -- 858
142. Written submissions from Ardbraccan witnesses -- -- -- - -- 859
-----------------------------------------------------
628
NAVAN BY-PASS SECTION
------------------------------------
86. Evidence of Susan Joyce, Project Engineer, MC O'Sullivans
Consulting Engineers for the Council :
86. 1. Examined by Esmond Keane B.L. for the Council :
Ms Joyce had previously given evidence as the Project Engineer for the Clonee to
Dunshaughlin section of the M3 Scheme, see Section 25.1. of this Report.
Ms Joyce said that the Navan By-pass Section commenced at the tie-in with the
Dunshaughlin to Navan Section to the south-east of Navan and proceeded in a northwesterly
direction to by-pass Navan to the south and west and crossed various County
roads, one Regional road (R161 Trim road) one National Secondary road (N51 Athboy
road) and joined the Navan to Kells Section to the north-west of Navan. She said the
Navan By-pass Section consisted of :-
8.5 kms. of 2 x 2 lane motorway by-pass of Navan
2.0 kms. of 2 x 2 lane dual carrriageway -- the Kilcarn road, linking Kilcarn
Interchange to the existing N3 in Navan
2.5 kms. of 2 x 2 lane dual carriageway -- part of the N51 Athboy Road
Realignment linking the Athboy Road Interchange to Navan
1.2 kms. of single carriageway --- part of the N51 Athboy Road Realignment
linking the Athboy Road Interchange to Clarkes Cross Roads
Grade separated Junctions ( Interchanges) at Kilcarn and at Athboy Road
Roundabout junctions at Kilcarn/N3 and at Athboy Road /N3
Structures including 9 Road Overbridges, 1 footbridge, 4 Underpasses and
2 Retaining Walls
Upgrading / Realignment of 7.5 kms. of existing National, Regional and
County roads affected by the proposed motorway
Assoociated ancillary works including culverts, road drainage, accommodation
works and environmental mitigation.
Ms Joyce said the Scheme details were shown in Volume 5B and she then gave a detailed
description of the route of the proposed M3 , which is generally set out in Section 12 on
pages 24 and 25 of this Report and is not being repeated in full in this Section. She said
the proposed Navan By-pass tied in to the Dunshaughlin to Navan Section at the
Cannistown road crossing at chn.41150 south of Cannistown Church where the
Cannistown road was realigned, as part of the Dunshaughlin to Navan Section, to cross
over the M3.
Ms Joyce said that the mainline levels had been kept as low as it was feasible to reduce
the environmental impacts and that, in general, it was the levels of the water table and
629
existing streams and the drainage design which dictated the extent those levels could be
lowered, with the requirements for underpasses and the geometric design criteria
resulting in some local raising of the alignment levels but that the design and location of
the underpasses were generally chosen to minimise the impact of raising the alignment,
where this was feasible. She said the Kilcarn Interchange was located south of Navan
between the Cannistown road and the R161Trim road and this would be a trumpet type
interchange with one bridge and with both north bound and south bound ramps which
would allow for entry and exit to and from the M3 in both directions. She said the Kilcarn
Road would tie-in to the east side of the Interchange and this road linked to the existing
N3 at a new Roundabout on the southern side of Navan near the existing Kilcarn Bridge.
She said the motorway was generally close to existing ground level from the Cannistown
road through the Kilcarn Interchange area and then continues westwards on an
embankment varying from 1.7 metres to 3 metres above ground level through Macetown
townland where it headed north-westward again on a low embankment through
Hanlonstown townland where it ran through a 3 metre cutting for some 400 metres. She
said that beyond this cutting the motorway was again on an embankment which rose to
4.9 metres above ground level in as it approached the existing N51 Athboy road in
Boyerstown townland which crossed over the M3 at this point. Ms Joyce said the Athboy
Interchange was located in Boyerstown townland to the west of Navan and to the north of
the existing N51 Athboy road and on embankment some 2 metres above ground level at
this point. She said a new realigned section of the N51 will link from the northern side of
Navan from a new Roundabout at Townparks through the Athboy Interchange to link
back to the existing N51 at Clarke's Cross Roads. Ms Joyce said the Athboy Interchange
would be a dumbbell type interchange with two roundabouts, one at either side of the
mainline, and a single bridge between these roundabouts. She said this would provide for
traffic movements in all directions and that the dual carriageway link to Navan at the
New Roundabout at Townparks would tie in to the eastern roundabout, with the new
single carriageway link to the Clarke's Cross Roads new Roundabout tying into the
western roundabout.
Ms Joyce said that beyond the Interchange the motorway continued north-westwards on
an embankment, of up to 3 metres above ground level in places, before entering a cutting
of up to 3 metres as it approached the Boyerstown road crossing, and continued at ground
level northwards beyond the Boyerstown road crossing until it entered a cutting as it
crossed the Halltown road and continued in cutting of up to 4 metres as it passed under
the Bohermeen road to the west of Ardbraccan Glebe. She said the motorway went onto
an embankment as it approached the Durhamstown road crossing and continued on
embankment of 2 to 3 metres above ground level as it tied in the the Navan to Kells
Section in Grange townland at chn. 49700.
Ms Joyce said there would be two new significant Roundabout junctions provided, the
new Kilcarn Roundabout on the N3 south of Navan which would be an urban junction
with dedicated left slip lanes to facilitate dominant traffic flows and the Athboy
Roundabout at in Townparks, about 1km. west of Navan Town Centre. She said this was
located at the intersection of the proposed Athboy N51 Realigned road (west), the
630
existing N51, the proposed Council Inner Relief Road Phase 2B, theTara Mines road,( L-
7418-16) and the link road to Gainstown road and this was also an urban roundabout
which tied the Link road into the existing and proposed local road network. Ms Joyce
also described the two new Link roads from the M3, the Kilcarn road and the Athboy
N51 Realignment. She said the Kilcarn road ran parallel to the Cannistown road from the
Interchange and crossed under the Ballybatter road ( L 8010-0) in a deep cutting and also
under Swan Lane (L 34141-0), which was to become a cul-de-sac with pedestrian traffic
maintained by a footbridge at that point, and tied in to the existing N3 at the New Kilcarn
Roundabout. She said the existing N51 was being realigned from Clarke's Crossroads all
the way into Navan and tied in to the local network at the New Townparks Roundabout.
She said the new Realigned Athboy road would run parallel to the existing N51and
generally ran through farmland with no side road crossings and it was on a 7 metre high
embankment where it crossed over the motorway at the Athboy Interchange. She said the
realigned N51 would be a single carriageway from Clarke's Crossroads to the Interchange
and continued as a dual carriageway from the Interchange to the Townparks Roundabout.
Ms Joyce then described the realignment works proposed on the various National,
Regional and County Roads that would be affected by the scheme and said that, in all
cases, the new carriageways would be at least as wide as the existing roads. A number of
these works would arise from the location of over or underbridges where the road was
crossed by the M3 such as the Trim Road (R 161), Robinstown Road ( (L 4007-0), N51
Athboy Road, Boyerstown Road ( L 8008-20), Bohermeen Road (L8009-6) and the
Durhamstown Road (L 4005-11). She said Swan Lane would be closed on either side of
the Kilcarn Link road with no direct access to Swan Lane from that Link road and some
ancillary works provided between Swan Lane and the proposed footbridge crossing the
Link Road there. She said the Gainstown Road (L8010-18)) and the Halltown Road
(L 80091-16) would both be made cul-de-sacs on either side of the M3 with a local
diversion on the Gainstown road but that none were required on the Halltown road since
there were no houses on that section. She said there would be some realignment required
on the N3 at the new Kilcarn roundabout and also at the Ballybatter Overbridge( L 8010-
0) where this crossed the Kilcarn Link.
Ms Joyce said that, as well as the two Interchange Overbridges, there would be 7
Overbridges to be constructed on this Section and she listed these as the Trim Road
R161, Robinstown, N51 Athboy, Boyerstown, Bohermeen, Durhamstown and Ballybatter
(Kilcarn Link) overbridges, with a Foot/ Cyclebridge at Swan Lane and 4 Farm
Accommodation Underpasses, one under the M3 for animals only at chn. 45860, one on
the Kilcarn Link for vehicles and animals at chn.1250 and Two on the Athboy road for
animals only at chn.200 and for vehicles and animals at chn.1550.
Ms Joyce said the details of the Motorway cross-section had previously been given by
Mr. Guthrie ( See Scetion 17.1. at page 69 of this Report) and she gave the following
details for the other roads in this Section. In the case of the Kilcarn and Athboy Road
dual carriageways the predicted traffic flows for the 2024 "do something tolled" scenario
was 22800 and 33500 AADT respectively and this required a standard dual carriageway
width, the same as that for the proposed M3, to provide for a level of service of "C". In
631
order to maintain consistency for drivers the section of the realigned single carriageway
N51 between Clarke's Crossroads and the Interchange would use the width of the existing
road and a carriageway width of 7.5 metrres with 2 no. hard shoulders of 3 metres and 2
no. verges of 2 metres was proposed, giving a total width of 15 metres excluding side
slopes. The cross-section of the R161 Trim Road was proposed to be the same as a
separate scheme for improving the Trim Road already prepared by the Council, and this
would use an 8 metre carriageway, 2 no. 0.5 metre hard strips and 2 no. 3 metre verges,
giving an overall width of 15 metres excluding side slopes. The cross-section for County
Roads would use that in Annex A of the NRA Road Geometric Handbook, for nonnational
roads with a reduced verge width and would generally consist of a 6 metre
carriageway and 2 no. 2 metre verges, giving a total width of 10 metres excluding side
slopes and this would apply to all of the county roads to be realigned as part of the
Scheme.
Ms Joyce said the Slip Roads, or ramps, at the Interchanges had their cross-sections
defined in the NRA document DMRB TD 27/00 and she gave the details as follows. For
all of the Athboy and for the northbound merge and southbound diverge lanes at Kilcarn
there would be a 4 metre carriageway with a 0.5 metre offside hard strip and a 1 metre
near strip with 2 no. 3 metre verges outside the strips. For the Kilcarn two lane
northbound diverge there would be 2 no. 3 metre carriageways with the same widths of
offside and nearside hardstrips and of outside verges. For the Kilcarn two lane
southbound merge there would be 2 no. 3.65 metre carriageways with the same widths of
offside and nearside hardstrips and of outside verges.
Ms Joyce said that they estimated some 454000 cu. metres of material would be
excavated, of which up to 89000 cu. metres could be unsuitable, and this would have to
be disposed of off-site or used in landscaping on the site. They estimated there would be
a deficit of fill material requiring the importation of some 785000 cu. metres into the site.
She said the location of the borrow pits for this fill material and any disposal sites for the
unsuitable material would be the responsibility of the Contractor and both disposal sites
and borrow pits might require that prior Planning Permission be obtained by the
Contractor for their use.
She said that the Navan By-pass Section crossed land that was mainly flat or gently
undulating and lay for the most part within the Boyne Catchment, and the River Boyne
was joined at Navan by the River Kells-Blackwater which rose north of Bailieboro.
She said the route crossed numerous drainage ditches and some small tributaries of both
Rivers. She said their preliminary drainage design indicated the following general
requirements :-
Appropriate culvert and bridge crossings to cater for intersection of existing
rivers and streams.
Appropriate outfall points had been identified for various sections of the roads
and the design discharges had been quantified.
Attenuation measures to be implemented at each outfall point had been identified.
The drainage criteria required to implement a satisfactory drainage system had
632
also been identified.
Ms Joyce then outlined the program of Public Consultation which they had used in their
study to identify and address the views of the public, which she said, included meetings
with interested parties and the public, the display of possible route options at different
centres and the distribution of a brochure and questionaire. She said written submissions
had been received from Residents Associations and Interest Groups as well as from
individuals and businesses, all of which were considered in the Route Selection process.
She said the first Public Consultation Meeting was held in Ardboyne Hotel, Navan on 24,
25 & 28 February 2000, with drawings showing 8 possible route corridors and known
constraints on display and that a presentation was made to the Meath County Council
Members in Navan on 21 February 2000. She said the second Public Consultation
Meeting was held in Ardboyne Hotel, Navan on 22 & 23 May 2000 and in the Headfort
Arms Hotel, Kells on 24 & 25 May 2000 and that this second Public Consultation was a
joint consultation for the 3 Sections between Dunshaughlin and Kells, namely,
Dunshaughlin to Navan, Navan By-pass and Navan to Kells. She said that at these
meetings the emerging preferred routes were presented, the likely impacts identified, the
public views and reactions were obtained and queries were responded to in the context of
the scheme development at that time. She said the meetings had been advertised in local
papers, on local radio and at Parish Churches, with leaflets also distributed and that about
2200 people attended the two consultation meetings. She said that after the second Public
Consultation the drawings were put on display in the County Library for a further 4
weeks and during this period Council's Design Team took written submissions and met
with the public.
Ms Joyce then outlined the Route Selection procedure and said that 8 possible
corridor/route options had been identified for the Navan By-pass Section, taking into
account the constraints identified in the Constraints Study, and said that four of these
routes were each on the east and west of Navan. She gave a brief description of each of
these routes as given in the Brochure used in the February 2000 Consultation ( Note -- a
copy of this was handed in to the Hearing on Day 18 and is listed in Appendix 4 of this
Report.) Ms Joyce described how each of the 8 routes was examined under engineering,
environmental, social and economic factors to identify a preferred route and she
concluded that Route A, the Purple route, was the preferred option for the reasons which
she outlined.
Note -- The comparison of possible options, the analysis to identify a preferred route and
the reasons for selecting the Purple Route are also given in Sections 4.2.3, 4.3.4 and 4.4.4
at pages 37-39, 44 and 50 in Vol.2 of the EIS and are not repeated in this Report.
Ms Joyce said that a number of the submissions were received included some from
residents in the Ardbraccan area which was where the Navan By-pass and the Navan to
Kells Sections interfaced and that at a meeting on 12 July 2000 the Council requested the
Consultants to undertake a a further study of this interface area to establish the optimum
line for the EPR there. Ms Joyce said that initially 4 route corridors were considered as
633
alternative options to the EPR in the Ardbraccan area and 3 other lines presented by the
public were then developed into a further 7 routes and also compared to the EPR. Ms
Joyce said that a total of 12 posssible routes were considered for the Ardbraccan interface
area and she desribed these as follows :-
Route A -- this was the EPR as presented to thePublic on 12 May 2000
Route 1 -- this was the initial route submitted by David & Sarah Maher,
Ardbraccan House on 13 June 2000
Routes 2, 3 & 4 -- these were developed by the Design Team
Routes FB1, FB2, FB3, FB4, FB5 & FB6 -- two routes known as Frank Burke 1 & 2
were submitted by Frank Burke, Consulting Engineer on behalf of Residents
of Ardbraccan on 20 October 2000 and these were extended to facilitate
having similar start and end points to the other route options for evaluation.
MD1 Route -- this was a route submitted by a landowner, Margaret Donaghy, in a verbal
description to an engineer in the Council's Design Office and this route was
similarly extended as the FB routes for evaluation.
Ms Joyce said that having assessed these options Route A was still the preferred route
and served the National road traffic demand with the least overall environmental impact
for a number of reasons, including the following :-
*This route impacted significantly less on residential buildings with only 5 buildings
within 100 metres of the roadc alignment.
*This route did not directly impact on any known NHAs or known archaeological sites
with most other routes impacting on known possible archaeological sites even if these
were not considered to be significant sites.
*This route had no impact on identified habitats for flora or fauna while some others had.
This route did not directly affect any known Historical or Architectural sites while some
other routes had some impacts on these.
*This route required a maximum of 4 bridges, or one less than most other routes.
*The construction costs, impact on 20 farms and design standards for Route A were
comparable to those of the other route options.
Ms Joyce then described the Route options considered for the N51 Athboy Road Link
where 5 options were examined all traversing the farmland to the north of the existing
N51 to meet the constraints dictated largely by the need to tie into the existing and
proposed local road network and to the Interchange on the M3; the proximity of Housing
and Industrial estates at Townparks and Mullaghboy and Tara Mines; Roadside
Development and Farm severeance; condition of existing road network and that no direct
access was to be permitted to the Link road. She said each route was examined under
engineering, environmental, social and economic factors to identify a preferred route and
she concluded that Route 3 was the preferred option, for the reasons which she outlined.
The principal reason for selecting this route for the Link road were that it had the least
number of houses within 200 metres of the route and it, with Route 2, was more
favourable in terms of farm severance than the other routes. Ms Joyce concluded that, on
634
balance, Route 3 was the preferred route for the Athboy Link road to Navan from the Bypass.
Ms Joyce said that 5 options were examined for the Kilcarn Link all of which generally
were parallel to the Cannistown road with 3 options crossing the Ballybatter road and 3
crossing the Cannistown road (i.e. one crossing both). She said 3 options crossed Swan
Lane, one crossed the Boyne requiring a significant bridge and another option used a
widened Cannistown road and three roundabout options for the N3 junction were
considered. She said the built- up nature and steep topography south of Navan made all
options difficult and the constraints were the urban nature and proximity to South Navan
and River Boyne; topography; condition of existing road network and no direct access to
be provided to link and provision for future up-grade of tie-in junction on N3.
Ms Joyce said each route was examined under engineering, environmental, social and
economic factors to identify a preferred route and she concluded that Route 4 was the
preferred option for the reasons which she outlined. The principal reason was that it had
the least farm severance impacts and it was one of three that had the second least number
of houses close to it, the route with the least houses directly impacted on Boyne Hill
House a house of Historical significance and in other respects it was similar to the other
options. Ms Joyce concluded that on balance Route 4 was the preferred route for the Link
road between the Lkilcarn Interchange and the N3 to thesouth of Navan.
Ms Joyce said that in responding to environmental need and the public's concerns the
alignments of some of the roads in the Section were re-examined and, that in some cases
the design was refined or revised with the more important measures which mitigated
significant adverse effects as identified by the EIS process were incorporated into the
Scheme. Ms Joyce then listed 17 revisions or amendments they had made to the Scheme
as a consequence of this review. These are all listed in Section 1.2 of Vol.5A of the EIS
on page 15 and are not repeated in this Report.
Ms Joyce said that the environmental impacts of the scheme were taken into
consideration at all stages of the project, with a Constraints Report which identified
environmental sites on the route corridor being produced prior to the Route Selection
process. She said that the EIS on the likely impacts on the environment had been
prepared in accordance with section 50 of the Roads act 1993 as amended by the EC
(EIA) (Amendment) Regulations 1998 and by the EC (EIA) (Amendment) Regulations
1999 and that this EIS contained a description of the proposal, alternatives examined, the
receiving environment, as well as assessing the principle beneficial and adverse
environmental effects that would arise from the construction and operation of the
Scheme. She said it gave details of the measures proposed to mitigate likely significant
adverse impacts as well as the beneficial environmental consequences and she then
outlined the principal findings on the various impacts. These are dealt with in more detail
in the Evidence presented by the other witnesses for the Council and reported on in the
following Sections of this Report.
635
Ms Joyce said that if the tolling proposal did not proceed the main difference would be an
alteration in the traffic flows and that a greater number of vehicles would be attracted
onto the M3, which would require some minor alteration to traffic lane layouts at some
junctions. She said that, while air quality and noise impacts were dependant on traffic
flows, the flow changes in the Clonee to Dunshauhghlin Section were not sufficient to
significantly alter the impacts identified for the Tolled Scheme. She said, however, that a
noise barrier some 1.5 metres high would be required on the Athboy road near the
proposed roundabout from chn.2200 to chn.2450
Ms Joyce said that there were 28 Public Rights of Way and 4 Private rights of Way to be
Extinguished and the details were attached to her Brief of Evidence. ( These are included
in the Lists set out in Appendices 6 and 7 attached to this Report ) Ms Joyce confirmed
that it was necessary to extinguish all those listed for the purposes of the Motorway
Scheme. She said that the landtake required for the Navan By-pass Section was some
132.4 Hectares of which some 58.3 Hectares were required for the actual Motorway with
the balance for non-motorway works and she confirmed that the acquisition of all of this
land was necessary for the M3 scheme. Details of the reasons for acquiring each plot
identified in the Schedules were given in Appendix D in Ms Joyce's Brief of Evidence.
Ms Joyce said she had prepared a folder that contained their response both to the original
objections that had been made and to supplementary objections submitted during the
Hearing and she said a copy of those responses had been posted out to all of the
individuals concerned at least two weeks previously. She then handed in a copy of the
folder of these responses to the Inspector . Mr Keane asked her to also hand in the folder
of resonses made to the supplementary objections received during the Hearing for the
Clonee to Dunshaughlin Section (Note -- These Folders are listed at Day 16 in Appendix
4 of this Report)
The Inspector asked if a Map showing the alternative routes suggested by the public in
the Ardbraccan area as referred to in her evidence be handed in and Ms Joycc said she
would provide this. ( Note -- This was included with the Constraints and Route Selection
Study documents for the Navan By-pass handed in by Ms Joyce on Day 20 as listed in
Appendix 4 of this Report).
The Inspector also asked Mr. Keane to arrange for the submission of a summation of the
total areas of land being acquired in the CPO and this was handed in on Day 28 as listed
in Appendix 4 of this report. Mr. Keane then handed in a copy of the accident data on the
N3 as previously requested by the Inspector from Mr. Guthrie (See Section 19.9) and
detail's of the water levels in Seamus Farrelly's well on the Hill of Skryne as referred to in
his verbal submission (See Section 84.1).
86. 2. Susan Joyce cross-examined by Sean Carty, Cannistown, Navan -- Plot 1136 :
Mr. Carty said his house was between 400 and 500 metres from the Williamstowm
Interchange (Kilcarn) which was elevated 8 metres above the ground and with cars
traveling uphill to the overbridge there would be a lot of gear changing and a lot of noise
636
and there was no noise mitigation there that he could see. Ms Joyce said there were two
places in the EIS that dealt with his area, the first being Table 4.6 in Vol.5A at page 78
and then in Figure 4.1.1 and that the impact was severe in the EIS with the existing noise
being 46 dB and this was predicted to increase to 62dB in 2004 and to 66dB in 2024. She
accepted the jump was significant but said it was below the cut-off of 68dB which was
why there was no mitigation because that was only put in when the noise exceeded 68dB.
Mr. Carty said he worked in Tara Mines and that for most of the time there he wore
eareplugs and earmuffs and his garden was the place he relaxed in when he came home
and that he would now have levels of 63dB to contend with.
Ms Joyce acknowledged his situation and agreed she would not like to have to wear
earmuffs at home and said the noise would be similar to that in a busy office if he took
this from Plate 4.1 in Vol.5A. She said she knew this was not much consolation for him
but said that when the prediction did not reach 68dB the practice was to provide no
mitigation and that while the increase was large, it was still below 68dB. Mr. Carty asked
if the cost of putting in banks to reduce the noise would be expensive and Ms Joyce said
she did not have a figure on that but if it had to be done it would be expensive as the
material would have to be brought into the site since they were short of material already.
Mr. Carty said the figures predicted were hypothetical and there was no-one coming to
check them and Ms Joyce said she had double-checked the figures and the 46dB was
what would be expected in a quiet rural area like his and that while the increase from 46
to 66 was significant the difficulty was that it was not over 68.
The Inspector commented that the issue of noise was likely to be raised again by Mr.
Macken as he would returning the following day and he had raised the Outer Ring Road
decision by An Bord on a noise restriction and when Mr. Butler said they now had a copy
of that decision and would be dealing with it, the Inspector said that he would be asking
for evidence of a written confirmation from the NRA indicating the statutory provisions
under which they were relying on the use of 68dB and that he was signalling this now.
86. 3. Cross-examined by Cannistown Residents Association :
Cannistown Residents Association were represented by Manus Tiernan, their Chairman,
and Jim McIntyre, a Committee member, and Mr. Tiernan said they represented an area
of between 150 and 200 households that was in the area between the Dunshaughlin to
Navan and the Navan By-pass Sections and they had to examine two sets of EIS
documents to see how they would be affected. He said they had been in consultation with
the Council through the design stages and had a number of meetings with them. He said
they had got the Interchange moved nearer to the Trim Road in the village of
Williamstown, or Bawn as it was known, and they had the Bective GAA football club
and the local school in their area. He said they still had a number of questions regarding
the impact of the motorway on their Community as some of their members felt some
questions had not been satisfactorily answered and said these generally related to the
construction stage, to the Noise issue and the Directive issued by the EU on 25 June
2002, the effects on Amenities in the area, Drainage impacts from the Williamstown
Interchange and Road Lighting effects, concerns about the cul-de-sacs at Ardsallagh and
637
Cannistown Roads and the need for footpaths. He said the Residents Asociation felt some
of the details in the EIS on habitats was inadequate from the Foot and Mouth restrictions
preventing surveys and wanted to know if these had been rectified since the restrictions
were lifted. He said the Association wanted assurances that cost would not take
precedence in putting corrective measures in place to safeguard the health and well-being
of the Community since the motorway and link roads would be there for generations to
come.
(Note -- As some of the queries relate to issues that were in both Sections, Alan Guthrie
responded where queries were appropriate to the Dunshaughlin to Navan Section)
Mr. Tiernan asked if there would be a temporary closure of roads in the Cannistown area
during the construction of the motorway. Mr.Guthrie explained that the Cannistown Road
was being realigned off-line so that there would not be a formal road closure but there
would be some disruption while both ends were being tied-in the the new section,. Asked
if this applied to the Ardsallagh and Botharalainnn roads as well. Mr. Guthrie said the
same situation applied to the Ardsallagh Road and Ms Joyce, having established that the
Botharalainn road was also the Balreask road, said that road would have to be closed
during the construction of the Kilcarn Link Overbridge on that road since it was an online
construction due to the houses adjacent to it. Asked for the timescale of the closure,
Ms Joyce said that it would be about nine months and that the existing local network
would have to be used as diversionary routes, with both the Trim and Cannistown Roads
being available. Mr. Tiernan asked what level of machinery would be used with the
construction of the Interchange, a cutting and two overbridges in the area and Ms Joyce
said she expected they were worried about construction traffic on the local roads and said
there would not be any since the Contractor would be limited to using National and
Regional roads which would be the N3 and the Trim road so that it was likely he would
start with the Kilcarn Link earthworks to create an access into the Section and she gave
an assurance that neither the Cannistown or Ardsallagh Roads would be used by
construction trafic either entering or leaving the site of the M3.
Mr. Tiernan asked where would the Contractors get their water from and if the Residents
could be assured their water and power mains would not be affected. Ms Joyce replied
that the Contractor would be obliged to keep services going at all times and he would be
expected to give notice of the periods where re-connections were being done when short
stages of disruptions to supplies might arise. Regarding the supply of bulk water for dust
suppression or other purposes, when Mr. McIntyre expressed concern that this might be
taken from the mains system, which suffered from low pressure in the Summer, the
Inspector intervened and said he would see it as being unusual for a contractor to use a
mains supply to fill tankers and said the more usual source for this was from the nearest
river or stream. When Mr. McIntyre asked for an assurance of this water not coming from
the public supply, Ms Joyce replied that it was highly unlikely to be taken from that
supply and the Inspector repeated that a contractor was not going to take it from a public
main when he would have to pay for it and that he would go to the nearest stream to fill
up instead.
638
Mr. Tiernan asked if access would be maintained into their area for local businesses, the
school and emergency services and when Ms Joyce said the Contractor would have to
maintain access but that there would be some diversions with the Ballybatter Road
(Balreask or Botharalainn) and Swan Lane closed and there would be some
inconvenience, Mr. Tiernan said many children coming to their school used the
Botharalainn Road and asked how would they have to travel when theat road would be
closed for nine months. Ms Joyce said they had considered the inconvenience which
would arise but there were major constraints in trying to do an off-line solution with the
deep cutting for the Link road, the railway bridge they had to preserve and with the
houses on both sides of the road. She said the Link was very significant for Navan in
overall terms with the traffic demand requiring two lanes in each direction and the
significant flow of traffic from Navan to Dublin requiring the link to be as close to Navan
as was possible and that all of this made the closure for nine months the best option in a
difficult decision. Asked if she was aware that traffic coming from Trim and going to
Dublin used the Botharalainn road, Ms Joyce acknowledged it was used as a "rat-run" at
present and said their traffic counts showed most of the traffic on the Trim Road was
bound for Navan with only 3 to 4% heading south towards the Dublin road. Mr.
McIntyre asked where the counts were taken and when Ms Joyce said it was an outbound
survey and south of Balreask crossroads, he said that did not address their concerns since
the traffic had taken a shortcut through Navan coming from Athboy, crossed the
Botharalainn and headed for Dublin and this avoided going through Navan and the
roundabouts on the by-pass. Ms Joyce suggested he was saying there were two choices
for that traffic of either going on the Cannistown road or staying on theTrim road and
crossing from Balreask to the Ballybatter road and she said that if the Ballybatter road
were closed, more were likely to use the Cannistown road. Mr. Tiernan pointed out that
the school was located at the junction of the Cannistown and Ardsallagh roads and that
the morning time had school traffic clashing with work related traffic and asked if they
had assessed the risk of major accidents occuring there.
Ms Joyce replied that they had not assessed that risk but they knew there would be
diversions onto both theTrim and Cannistown roads once Ballybatter was closed and said
that there was no other feasible solution to the short term closure. She felt that once the
Interchange was in place that Dublin bound traffic would find its way onto that and move
off the Cannistown road and she repeated the constraints they had faced with a 10 metre
cutting to be crossed and the railway bridge and corridor to be preserved and said that if
they could have left the road open they would have done so, as they had been able to do
in almost every other crossing. Mr. McIntyre said they accepted it was not feasible to
leave the road open but their concerns were of what was being put in place as an
alternative to accommodate morning time traffic. He pointed out how a three minute
drive to school in the morning could now become a 45 minute drive and he described
how this could happen and said his question was directed more at the County Council
rather than to the Consultants as it related to the planning of traffic management of Navan
for a nine moth period at least. Ms Joyce said she could see where he was coming from
but that the traffic figures for Ballybatter were not that large and, while it would create
local inconvenience, she felt that with signs it should be possible to adequately divert the
traffic onto the local road network.
639
Mr. Tiernan said their concerns were for the safety of their children at the school and that
if traffic was increased there should be a traffic management plan in place and said that as
there were no evidence of this in the EIS they were looking for assurances this plan
would be in place if traffic was going to be diverted into their area. Ms Joyce said her
colleague had pointed out that the Contractor might use the Trim road as a diversion
during construction and they could look at that and also because the Trim link road had to
be built in advance there was a possibility of phasing this as a diversion for the
Ballybatter traffic and said she would look at this in more detail. The Inspector
intervened and said since this traffic was for a rush hour period only and probably all
one-way there was also a possibility of a temporary diversion road being put into the
fields on the town side of the Ballybatter road and to take the traffic around the bridge
site while it was being built. He said he accepted this would need filling to be put in there
and that traffic lights might be needed and it would not be to geometric standards but it
might be a workable option, particularly if they got some more land. Ms Joyce
highlighted difficulties with retaining walls and the objection by Balreask House who
wanted the landtake from them reduced and following some further discussions on
possible solutions, the Inspector said that it seemed traffic management arrangements
needed to be looked at by the Local Authority and the Contractor and Ms Joyce said she
would consider the points raised and come back at a later stage ( Note -- Ms Joyce
handed in her comments on the Ballybatter traffic management /diversion arrangements
on Day 23 and these are listed in Appendix 4 of this Report).
Mr. Tiernan asked if there were proposals for a compound for construction vehicles in the
Cannistown road area and how much fill was needed and where would it come from. Mr.
Guthrie said there were no identified areas for construction plant compounds within the
scope of the EIS and it was up to the Contractor to make his own arrangements within the
limits of the CPO and said that if he wished to go elsewhere he would have to make a
perivate arrangement with land owners. Asked if blasting or piling had been identified,
Mr. Guthrie said they had not identified any rock south of the Cannistown road so
blasting was not anticipated but there would be piling for the foundations of the
Cannistown and Ardsallagh Bridges. Mr. Tiernan asked about vibration studies on the
effects of piling and Ms Joyce quoted from section 4.12 of Vol.3A on page 99 about
vibration impacts and said the same comments applied for each section and said that there
were "peak particle velocity" guidelines in Table 4.10 which would be the limiting
factors for vibration effects and Mr. Guthrie stated these would be monitored by the
Council supervisory team. Ms Joyce then gave details of the quantities of filling, which
were given in her Brief of Evidence, and said that the location of borrow pits and disposal
sites would be the responsibility of the Contractor and subject to the relevant legislative
requirements. Mr. McIntyre said he presumed this issue had been discussed previously
and the Inspector said that it had and that both sides of the argument had been put
forward and that An Bord would make its ruling on whether the EIS was adequate or not
in due course. Mr. McIntyre said they just wanted their concerns to be noted.
Mr. McIntyre then asked if the Consultants were familiar with EU Directive 2002/49/EC
issued on 24 June 2002 and when Ms Joyce asked if that was a noise directive and Mr.
640
McIntyre said it was, she said she would like if their noise expert would deal, with that
question and Mr. Keane said that Mr. Dilworth could be made available later on that day
if necessary but would be at the Hearing on the following day anyway. Following some
discussion on his availability, the Inspector said he could raise their concerns and then it
could be seen when the Council could respond.
Mr. McIntyre said that he would be making a personal submission at a later stage and
said the Association's concerns were that the noise levels of 68 decibels being used in the
design of the motorway were the highest in Europe at present and only the UK and
Greece had levels similar to Ireland. He quoted figures from Austria of 60 in daytime and
50 at night; from Denmark and Finland of 55 day and 45/50 at night; Germany of 59 day
and 49 night; the Netherlands 55 day and 45 night; Portugal 65 day and 55 night; Sweden
55 and the UK 68. He said he understood the Directive suggested certain measures had to
be put in place over the next number of years that would reduce the Ireland/UK/Greece
levels to a more reasonable EU average and he suggested that the Countries which were
now 45, 50, 55 would not be increasing their levels. When Mr.McIntyre asked if that was
their understanding Ms Joyce said she thought Chris Dilworth would be best placed to
answer that query and the Inspector said he recalled Mr. Dilworth saying there was a
Directive coming which signaled the start of harmonisation and he should be able to
elaborate. Mr. McIntyre said that from his background noise was a sensitive issue and
that the June Directive would cost aviation authorities and airline operators a lot of
money to become compliant with what he believed would be the outcome of this
Directive. He said we were members of the EU for 30 years now and were going to spend
a lot of money on this motorway and suggested that, rather than waiting to be told in a
few years time to improve the mitigation measures now being put in, we should be
anticipating what would be required to get us compliant with the EU average. He said he
was not saying that we should go down to levels of 45 or 50 but we should pick the
average and build the motorways and slip roads to be compliant with the EU average and
not to the highest levels available at this moment in time.
Mr. Tiernan asked what mitigation measures were being proposed at the Interchange and
slip roads as there were a lot of houses nearby. Ms Joyce explained that while the EIS
acknowledged the noise impact from the Interchange was severe, since the predicted
level was below 68dB no mitigation measures were being installed there and she referred
to Table 4.6 and Figure 4.1.1 and station points 29 and 2. A discussion followed with Mr.
McIntyre on the possibility of mitigation if different standards were to be applied and Ms
Joyce accepted it would be possible to put in noise screens but said she could not say to
what level a reduction could be achieved as that would be Chris Dilworth's area. She did
point out that there was extensive landscape screening at SLM 1 on Figure 5.1.4 and in
Table 5.5 in Vol.5A at Kilcarn Interchange. Mr. Guthrie said there were a series of noise
barrriers varying in height for 1.5 to 3.5 metres running from east to west as the old
Cannistown Road was crossed to give protection to the properties there, which he
indicated on the screen at the Hearing, and Mr. Tiernan asked about the length involved
and Mr.Guthrie said that the bunding was about 250 metre long from Cannistown road
towards the interchange and Ms Joyce said there was no bunding beyond that since the
641
noise levels were not predicted to exceed 68dB. Asked if there was screen planting Ms
Joyce referred to SLM 1 & SLM 2 in Vol.5A and showed these to Mr. Tiernan.
Mr. Tiernan referred to the amenities in their area like the Bective GAA club, Tara Golf
Club and Dalgan Park and asked for assurances that access to these would not be
interfered with during construction. Mr. Guthrie said that one of the reasons for the offline
construction of the realigned Cannistown road was to maintain local access during
the construction phase and that other for some disruption during the tie-ins there would
be access at all times to the football pitch and he said there would be a new footpath
along the full length of the realigned road. Mr. Tiernan asked if the footpath would be
extended to the school but Mr. Guthrie said that was outside the limit of their works and
was something they should raise with the Council. Mr. Tiernan suggested that this should
be done, as there would be more traffic and with the closure of the Botharalainn road but
Mr. Guthrie said this was outside the scope of their scheme.
Mr.Tiernan referred to the drainage from the Interchange area and asked how this would
be dealt with as it was on a well-known wetland. Ms Joyce said that all of the motorway
drainage would drain to a pond that was located in the centre of the Interchange at the
loop but Mr. Tiernan wanted to know how local drainage would be affected and Ms
Joyce referred to their drainage drawings in the EIS and described how they had
attempted to balance between the visual impact by keeping the road as low as poossible
and yet keep it high enough to be able to drain it and the concerns to have it moved away
from the football pitch and Cannistown so the pond acted as a sump for the Interchange
loop road and ramps and the motorway to the north with the road to the south going into
the Dunshaughlin to Navan drainage system. Asked where the water in the attenuation
pond went to, Ms Joyce said it stayed in the pond and said that David Wilson, their
Drainage Engineer, would be better able to explain the workings of the pond.
Mr. Tiernan asked what would happen if their septic tanks were affected by the
construction work and Ms Joyce said that where there was direct impact the tanks and
precolation areas would be re-located but otherwise there should be no effect on the
operation of these septic tanks. Mr. McIntyre asked if the construction of the Kilcarn
Link and the motorway would affect the level of the water table and Ms Joyce said it
should not but that she would have to check the borehole results before giving an
absolute clearance and said that from memory there was only one location on this Section
where there could be an impact on the water table and that was at the northern end. She
said they had identified what might be regarded as high risk areas for wells and they
would be monitored on an on-going basis and said that if there were impacts, the wells
would be deepened or what ever was the most appropriate solution.
Mr. McIntyre asked if there would be an independent arbitrator to resolve any problems
the residents had with the construction works. Ms Joyce explained how there would be a
liaison person who would be available to the public as their point of contact for
complaints and problems and that the Resident Engineering staff would also be checking
the contractor against the contract conditions and said there would not be an arbitrator as
such. Mr. Tiernan asked about the proposals to stop illegal parking and dumping on cul642
de-sacs and Mr.Guthrie said that any redundant road surfaces would be ripped up and
topsoiled and returned to the local land owner unless they were neeeded for access as had
earlier been stated. Mr. Tiernan asked what type of fencing would there be on the
overbridges and Mr. Guthrie said there would be parapets which would be 1.5 metres
high and with a steel mesh infill to prevent people climbing on them.
Mr. Tiernan said the Residents Association believed that there was insufficient
investigation of habitats and said that there was very little mention of the likes of
pheasants, squirrels, owls and badgers which lived in the wooded areas around
Cannistown. Mr. Guthrie said there had been surveys by their flora and fauna expert and
he had identified bats and badger locations and felt the other species would have been
generally dealt with and said that as they were not protected species they would not
necessarily be mentioned in detail in the EIS. When Mr. Tiernan suggested the survey
was incomplete due to foot and mouth restrictions, Mr. Guthrie said that surveys werc
done on the disused farm buildings at the old railway bridge at Cannistown and near
Bellinter Bridge for badgers, so that surveys were carried out. Ms Joyce said that there
were references to surveys in Vol. 5A and she quoted from this at page 188 about badger
activity along the Cannistown road, at chn. 40000 and chn. 950 about the need for further
investigations and several other references to hedgerows, trees identified as bat roosts and
so on. Mr. McIntyre said his concern was that a detailed inventory of the flora and fauna
in the area should be undertaken as part of the EIS and he understood the EIS said the
foot and mouth stopped some of the data being compiled. Ms Joyce then found the
reference he was relying on which was in paragraph 6.2 of Vol.5A, but that also said that
further surveys had been undertaken in September 2001 which, she said, showed that
they had gone back after the foot and mouth.
Mr. Tiernan asked what had they raised with the ERFB in the consultation they had as
there was nothing in the EIS to state what the ERFB had been asked about. Mr. Guthroe
replied that they presented their proposals for the Bellinter Bridge crossing and the
culverting of the Skane and Lismullin Rivers to the ERFB and discussed these in detail
with them to establish what their requirements were and the ERFB had set out their
structural requirements in the response Mr. Tiernan referred to. Mr. Guthrie gave as an
example the request by the ERFB to keep piers out of the River Boyne Channel and for
bottomless culverts on the Skane and Lismullin Rivers where salmonids had been
identified and said this was in the EIS, which was the outcome of the consultation. Mr.
Tiernan asked if the two streams in Cannistown had been examined and said one of these
flowed past the attenuation pond. Ms Joyce, having been given details by her colleague
said that there had been two sampling sites, 4 & 5, on those streams and they were shown
in Figure 7.1.1.
The Inspector said that from a reading of the EIS birds such as pheasants, wood pigeons,
blackbirds and others were mentioned in it as well as various mammals such as fox, hare,
hedgehog and others and he said the EIS appeared to have referred extensively to birds
and wild animals and gave mitigation measures for them. Mr. Tiernan asked about red
deer and the Inspector said deer were specifically mentioned in the EIS and Mr. Keane
said the reference was on page 102 in Vol.4A and at page 102 in Vo.5A as well. Mr.
643
Tiernan said their concerns were listed in their submission and he handed in a copy of
this. ( Note -- This is listed at Day 19 in Appendix 4 of this Report ).
86. 4. Cross-examined by Jim McIntyre, Boyne Hill, Navan on his own behalf :
Mr. McIntyre asked why the proposed new road behind his house was raised significantly
above ground level and asked if this was because of a cattle underpass. Ms Joyce replied
that his property actually straddled the interface between the fill area and the cut area and
said the underpass was at chn. 1520 and said they were trying to keep the road as low as
possible while facilitating both the underpass and getting under the Ballybatter Road
without affecting the level on the existing Ballybatter Road where there were several
houses. Mr.McIntyre suggested that in doing this the gradient down to the N3 was being
increased and Ms Joyce said it was 3.5% and they could go steeper than that to about 4%.
Mr. McIntyre asked if they could lower the new road to bring it down to the existing
terrain but Ms Joyce said the extent of the embankment at present went to the corner of
the properties on the Ballybatter Road around the crossing point and said that was the
only opening they could get to cross under it. She said they had discussed this Road
crossing with the Cannistown Residents Association who wanted the road kept open. The
closeness of the houses meant keeping the existing levels on the Ballybatter Road
unaltered so that dictated the level of the new road at that point and the under-pass had to
be facilitated as well.
Mr. McIntyre said that if the cut at the crossing was dropped by a further 2 to 3 metres
the new road could be dropped to ground level behind his house and those houses she had
been referring to would not be affected by this. Ms Joyce pointed out that such a further
reduction would mean a deeper cutting further on and would affect the side slopes on the
embankments which were designed at a one in two slope. She said they were presently
infringing on the corner of Balreask House grounds and on the entrance to another house
and any further reduction would increase that infringement and the impact. Mr. McIntyre
suggested that it was not necessary to keep to a one in two slope all the way down but Ms
Joyce said that would increase costs since a retaining wall would be required and said
there were also design problems with the vertical curve. Mr.McIntyre said that if the cut
was deepened there would be no problem with a vertical curve because the road could be
graded all the way down to the N3 from the Interchange and when Ms Joyce outlined a
further design problem, Mr.McIntyre suggested the underpass could be replaced by an
overpass. Ms Joyce said that underpass accommodated three landowners, M/s Keoghs,
Paul Foley and Frank Foley and moving the underpass increased the impact on them. Mr.
McIntyre suggested the underpass could be moved further south and said that might have
less of an impact.
When Ms Joyce said his proposal was basically to raise the road elsewhere and lower it at
his house, Mr. McIntyre said what was being proposed did not make sense to him as a
continuous gradient would be better from a drainage aspect and could have the underpass
closer to the Foleys or an overpass could be located where there was suitable ground for
it that he pointed to. At that stage the Inspector intervened and said that he thought there
was merit in what Mr. McIntyre was suggesting but it needed time to be properly
644
investigated and that it could not be designed by discussing the possibilities at the
Hearing. He said the CPO line and the houses were a constraint and there were obviously
cost implications from deepening the cutting if a retaining wall was needed. The
Inspector said that rather than debating it further the Council should look at the
possibilities of what was suggested by Mr. McIntyre and that they could come back the
following week with a suggestion or assessment. He told Mr. McIntyre he could discus
the points he was making with Ms Joyce if he wished.
Mr. McIntyre concluded his cross-examination by saying to the Inspector that he wanted
to put something about the NRA website on traffic noise to him and said that in the
various sections of that site where it said "the most" he believed it should read "the least
commonly used". The Inspector said he would note this submission but said if he wanted
that to be sent in writing to the NRA he would have to do that himself as it was not a
matter for him, as the Inspector, to do this.
86. 5. Susan Joyce cross-examined by Stephen Gunne, Auctioneer on behalf of
Sean Murtagh, Boyerstown, Navan --Plot 2181 :
Mr. Gunne said Mr. Murtagh was one of the few people who had a notice served on him
for a forfeiture of € 5000 for failing to allow the Council onto his lands and that his lands
were being severed and he was being provided with a shared access with Plot 2180. He
said Mr. Murtagh would have to travel for about 900 metres to get around to his lands
and his farmyard was on the other side of the Athboy Link Road. Mr.Gunne said he
would have about 65 to 70 acres severed across the road with about 25 acres left on his
own side and suggested that he should have been given a farm overbridge as against the
addition of nearly a kilometre and the underpass to get to his lands. Ms Joyce said they
had looked at that but a farm bridge would have cost over € 900000 when the underpassc
cost about €50 to 60000,but she said that it was not only on costs but because his farm
was all in grassland and there would not be cattle being moved on a daily basis. Mr.
Gunne said that Mr. Murtagh considered he should be given the same treatment whether
he was a dairy farmer or not but Ms Joyce explained that an access was provided where
the lands were being severed and in this case the most economic was an underpass .
The Inspector intervened and asked for clarification on the area of severance and was told
that the total area was 107 acres with about 9 being taken for the road and 70 acres
severed Mr. Gunne said the lands were let for over two years since Mr. Murtagh had been
in ill-health and that all of the land was used for grazing dry stock. Following further
discussion between Mr. Gunne and Ms Joyce about the costing for an overbridge and the
suggestion of Mr. Murtagh offerring to cede lands necessary for this at no cost, the
Inspector suggested that the farmyard appeared to be in the larger area of land and Mr.
gunne confirmed this was so and the Inspector commented that with the farmyard being
in the 70 acre part, the severance was on the 25 acres and not as was being implied on the
70 acres. He also said it was a dry stock farm and when Mr. Gunne said he accepted that
but said the house was between the yard and the road, the Inspector commented that the
livestock were not living in that house and Mr. Gunne acknowledged that.
645
87. Submission by Frank Burke, Consulting Engineer, regarding
proposed Closure of Swan Lane, Navan :
One of the submissions to the EIS was from M/s Steen O'Reilly & Co. Solicitors Navan
on behalf of Ronald Sherlock, t/a Sherlock Furniture, Balreask Old, Navan who objected
to the proposed closure of Swan Lane by the extinguishment of the right of way at its
eastern end ( See Section 13 and Appendix 6 of this Report). Mr. O'Donnell B.L.
appeared for this objector at the Hearing and Mr. Burke also acted for him.
On Day 22 Mr. Burke advised the Hearing that agreement had been reached between Mr.
Sherlock and the Council on the details of an alternative access arrangement which
provided for a private access road being constructed, 6 metres in width with a 4 metre
paved surface through Plot 2121 with gates at both ends. This private road would only be
used by Sherlock Furniture in accessing and egressing their factory. Details of the Points
of Agreement from which the objection to the extinguishment of the right of way was
withdrawn were handed in to the Hearing by Frank Burke on behalf of M/s Sherlock
Furniture on Day 22 and are listed in Appendix 4 of this Report.
88. Evidence of Philip Farrelly, Agricultural Consultant for the Council :
88. 1. Examined by Esmond Keane B.L. for the Council :
Note -- As Mr. Farrelly had already given evidence for the Council on the Clonee to
Dunshaughlin and Dunshaughlin to Navan Sections and as some of this is common to his
evidence on this Section, only the parts in his Brief of Evidence that are specific to this
Section are given in this Report.
Mr. Farrelly said said his Brief was to carry out a detailed assessment of each farm along
the selected routes impacted by the proposed M3 on the Navan By-pass Section for
inclusion in the EIS and to assess the macro effect of the proposed scheme on agriculture
locally and nationally for inclusion in the EIS. Mr. Farrelly said there were 47 farms
impacted on by the Navan By-pass Section with each of theses visited by a consultant
who interviewed each owner or occupier, using a set questionaire for all of them, with a
map of each farm showing the M3 impact prepared and a report prepared for each farm.
He said these reports were summarised in Table 10.6 in the Material Assets section in
Vol.5A of the EIS with the full details in Appendix G of Vol.5C of the EIS.
Mr. Farrelly said they examined the nature and style of agriculture along the proposed
route corridor in the macro report, which commented on the soil types encountered and
specifically on the Soil Associations in the effected area, and that agriculture in the DEDs
along the route was examined and compared to agriculture locally and nationally. He said
that the soil types encountered were principally Soil Associations No. 38 and 40, as
defined on the Soil Association Map of Ireland, which were characteristically fertile and,
when well drained, were suitable to a wide range of crop production. He said that no
646
farming enterprise along the route was so severely severed as to render it non-viable and
that no farm of national or local importance was being impacted in a way that would
make it non-viable.
Mr. Farrelly said that the impact of the scheme would be felt by individual farmers and
farm units rather than nationally or regionally and that the area being acquired was
insignificant in terms of the national agricultural area or the agricultural area in Co.
Meath.
89. Evidence of Chris Dilworth, Director, AWN Consulting Ltd.,
Environmental Consultants on behalf of the Council :
89. 1. Examined by Esmond Keane B.L. for the Council :
Note -- As Mr.Dilworth had previously given evidence on Noise and Vibration for the
Clonee to Dunshaughlin Section, some of his general evidence about assessment
procedures and mitigation measures is not repeated here.
Mr. Dilworth said they had been commissioned to conduct a detailed appraisal of the
noise and vibration impacts associated with both the construction and operation of the
Navan By-pass Section of the proposed road scheme. He said the existing noise climate
was quantified by baseline noise surveys which were conducted in accordance with the
survey methodology set out in the Calculation of Road Traffic Noise (CRTN) published
by the Department of Traffic, Welsh Office in 1988 and measurements were performed in
the vicinity of noise sensitive locations close to the proposed scheme. He said the primary
contributor to noise build-up was found to be road traffic with contributions from
livestock, wildlife and occasional aircraft and he said that the measured noise levels were
typical of those found in this sort of environment with no significant sources of vibration
being observed.
He said that it was generally not possible to conduct detailed construction noise and
vibration prediction calculations at the EIS stage of a development, as the program for
construction works was not sufficiently advanced and that the current best practice
dictated consideration be given to practicable mechanisms for controlling likely sources
of noise and vibration. He said that a variety of items of plant would be used in the
development and that rock breaking might be required on occasions. Mr. Dilworth said
that guidance on practicable control measures would be taken from BS 5228, Noise and
Control Measures on Construction and Open Sites, Part 1, Code of Practice for Basic
Information and Procedures for Noise and Vibration Control, 1997 and, where applicable,
reference would also be made to the EC Construction Plant Permissable Noise Levels
Regulations 1988. He said that typical control and compliance measures could include
the appointment of a site representative for noise and vibration matters; fitting effective
silencers to plant exhausts and pneumatic tools; selecting plant with low inherent
potential for noise generation; shutting down machinery rather than permitting it to idle;
limiting the hours during which specific activities such as piling might be conducted;
647
conducting noise control audits in accordance with BS 5228; communicating with local
residents and monitoring levels of vibration during critical periods and at sensitive
locations.
Mr. Dilworth said that traffic noise predictions for the proposed scheme when in
operation had been conducted for 2004 and 2024 in accordance with CRTN methodology
with traffic noise levels predicted for 20 locations as being representative of the closest
noise sensitive locations along the route. He said the predicted levels had been compared
to the target criterion of 68 dB LA10 18hour, which was the current best practice
advocated by the NRA. He said mitigation measures were deemed necessary whenever
the scheme had a nett negative impact and the predicted noise level was greater or equal
to the target criterion. He said this target of 68dB LA10 was neither met nor exceeded for
the tolled scenario at any receiver but that mitigation measures were required at one of
the locations assessed for the untolled scenario. He said the proposed mitigations
consisted of solid roadside barriers, the details of these being set out in the EIS and the
resultant predicted traffic noise levels satisfied the target criterion at all locations.
Mr. Dilworth said that it had been found the ground vibrations produced by road traffic
were unlikely to cause perceptible structural vibration in properties located near well
maintained roads and that maintaining the road surface would ensure vibration was not
significant.
He said that mitigation measures were required for one location under the untolled
scenario and this consisted of a solid barrier 1.5 metres high that ran from chn.2200 to
chn.2450 along the proposed Athboy Road and satisfied the target criteria. He said that
no further mitigation measures arose from the assessment for the Navan by-pass Section
but he said the cumulative noise level associated with the Navan By-pass Section when
combined with the Dunshaghlin to Navan Section was such that further measures were
required. He said this mitigation consisted of a solid barrier 3.5 metres high that ran from
chn. 41050 to chn.41300 alongside the southern carriageway and this satisfied the target
criterion.
Mr. Dilworth then referred to the "Errata sheet" which he had prepared and which
superceded Tables 4.2 and 17.4 and Tables 4.6 and 17.5 in Vol.5A of the EIS. He said
that the reasons for the "errata sheet" were given on it and this arose from incorrect
descriptions of two of the links being given and one of the links being missing, which had
now been corrected in the "Errata sheet" . He said that, essentially, the descriptions for
the top two lines in table 4.2 were misplaced and the link for the N3 north of Navan, the
third line, was omitted. He confirmed that there were no materially different results and
no values of significane as a consequence of these typographical errors.
( Note -- The Errata Sheets handed in to the Hearing are included in Mr. Dilworth's Brief
of Evidence which was circulated on Day 5 and read to the Hearing on Day 15)
648
89. 2. Chris Dilworth cross-examined by Jim McIntyre & Manus Tiernan
of Cannistown Residents Association :
Mr. McIntyre asked if he was familiar with EU Directive 2002/49 EC of 25 June 2002
and when he said he was, asked if he could explain this in layman's language. Mr.
Dilworth said the Directive was one of the first instruments in an on-going process across
the EU to homogenise noise and said there were two thrusts to it, the first being a
proposed change in parameters to Lden which was the day/evening/night and Lnight
which was the night time parameter and the other was a protocol on noise mapping. He
explained that the noise mapping set out the circumstances where Member states would
map environmental noise from various sources such as rail, airports etc and present the
results with mitigation proposals to reduce exposure of persons to noise. He said there
were various steps to the exercise with criteria set for the level of traffic on a road or size
of airport requiring mapping and that by 2007 there had to be a report back, with further
stages by 2012 when the noise maps and mitigation measures were to be put in place.
Mr. McIntyre asked if he believed the provisions of 2002/49/EC should be considered if a
motorway was being built today and when Mr. Dilworth said "no", asked why not. Mr.
Dilworth said it was a question of prematurity as there was no guidance on what would
be the national methodology or proposed criteria or assessment methodologies. Mr.
McIntyre asked if he was paying him would his answer be different and Mr. Dilworth
said it would not and he was already being asked that by some clients and his advice was
that the Directive set out clear time scales. He said that for a scheme like the M3 where
planning started some time ago it would be premature to have used an as-yet unpublished
Directive. Mr. McIntyre suggested this Directive went back into the early 1990s and Mr.
Dilworth said that was when discussions commenced but the working groups which
produced the present Directive started later. Mr. McIntyre asked if the roads should be
designed to best European practice rather than using the highest decibel levels in Europe,
which were only used in Greece and the UK as well as in Ireland. Mr. Dilworth said the
Directive acknowledged there were differences and that it was appropriate for the
relevant authorities within Member States to set the criteria which meant localised
criteria. Mr. McIntyre referred to the "euro" and said if we had one currency why should
there not be one noise level. Mr. Dilworth said that was for the EU and his argument was
that you designed to an acceptable standard and said the present one represented an
acceptable level, but he agreed there could be a case argued for a more stringent level.
Mr. McIntyre referred to the modifications that airports would have to do to meet this
Directive and asked why was the motorway being built to a standard that would have
then to be modified within the next 2 to 12 years but Mr. Dilworth said it was being built
to standard practice and that to design to a hypothetical future level was premature and
not the best practice. Mr. McIntyre quoted the criteria from other European countries
(which he had previously quoted in Section 86.3 )and said all motorways in Ireland were
being built to a criteria that was 8 to 10 decibels above the European average and asked
why should he be asked to support the building of one at his backdoor where it would be
necessary to spend more money in 3 to 7 years time to replace the barriers to comply with
649
EU legislation, which he suspected would put the level in the low 50s but not in the high
60s. Mr. Dilworth said he had quoted a lot of figures, probably from the same Table as he
was looking at, and there were different parameters and different time scales used for
most of them and most were free flow rather than façade levels. Mr. McIntyre said some
had façade levels and Mr. Dilworth replied that some were LA10, some LA and most
were LAeq and it was not comparing like with like.
Mr. Dilworth said free field was 5 decibels below LA10 so 68dB LA10 was really
63LAeq so the comparison should be with that figure. He said the question of why 68dB
was being used was a policy one and not for him to justify. He said that he considered it
was an appropriate level but that was not to say it would not be changed to a lower figure
at some future time. He said that it was possible the EU would continue to allow each
member state to fix its own level so it could still be an Irish limit would be used. He said
that in his opinion it was very unlikely that we would ever go into the low 50s and that
55 was the lowest he would envisage and said that 60dB seemed to be the more likely
figure, if an EU wide level was chosen. Mr. McIntyre said he was agreeing with him that
55 would be a more sensible level but Mr. Dilworth said he was saying that 55 would be
a more stringent level and that there were arguments for and against it and he would
reiterate that the current level of 68 LA10 or 63 LAeq was still appropriate.
Mr.McIntyre said the Directive gave guidelines and that certain elements of it would
happen in time but that it was effective now and when he was told that the UK CRTN
method was used in Ireland, he said the Directive stated the French national computation
method should be used and the French limits were 60/65 in daytime and 55/57 at night
and that he wanted those limits applied. Mr. Dilworth accepted the Directive was
published in June 2002 and that it made a recommendation but said the M3 scheme had
been designed some considerable time before that. Mr. McIntyre said the people living
along the route of the M3 were those who would be affected and that as the road might
not be built for several years, if ever, the EU Directive criteria should be used, not
historic criteria. Mr. Dilworth said that if a policy item was being considered and he was
consulted he would then offer an opinion but at this stage he had not, and did not intend,
recommended that there would be a re-computation using the French Standard.
Mr.McIntyre asked how long would it take to do this, if he were to be asked to do so and
Mr. Dilworth said it would take three to four months to complete. Mr. McIntyre asked if
he accepted the existing mitigation measures behind his house would have to be changed
if the French national standard for computation was used. Mr. Dilworth replied that he
would not comment on any specific situation as an analysis would have to be done, but
said he would accept that any change in the target level would make it likely that
additional measures would be required.
Mr. Keane intervened and asked Mr. McIntyre to indicate where in the Directive did it
say that the French computation method was to be applied, as he had the Directive in
front of him and could find no such reference and he quoted several extracts from the
Directive. Mr. Dilworth said that he understood there was a provision that where a
country did not have its own standard or policy then the French method of computation
should be used as a default. He explained that the standards and method of computation
650
were two separate things with the method of computation only saying how noise levels
were to be calculated and it had no limits given in it as these were in a different document
which was the standard used. Mr. Dilworth said he had no recollection of the Directive
saying the French standards should apply but the computation method was the default
method.
The Inspector intervened and said that for the purposes of the Hearing Mr. McIntyre had
outlined that he considered standards lower than the 68dB should be used and the
Council's case was that they were following the accepted practice. He said that it
appeared as if the French method of calculating noise was contingent on something else
not being specified and that did not affect the basic argument which was the mitigation
level should be set at a lower level. Mr. McIntyre asked if he was right in thinking there
had been another occasion where levels below the 68 had been applied and the Inspector
said there had been reference earlier on that Day of the Outer Ring Road case in Dublin
where there was an additional level below the 68 dB LA10 applied by An Bord but that
construction of that road had not yet started so it would not be accurate to say it was in
place.
Mr.McIntyre asked if he considered there would be a limit in place of between 55 and 60
at some time in the next 5 to 10 years but Mr. Dilworth said that it might be left to
individual Member States to set their own limits and that he could not bank on there
being an EU wide limit. When Mr.McIntyre suggested the present differences ranged
from 45 to 68, Mr. Dilworth said he was not comparing like with like and that the present
range across the EU was 55 to 65 LAeq for daytime and 45 to 57 LAeq for night time and
said that by designing for a daytime 68 LA10, which was 65 LAeq, this gave a typical
nighttime level of 10 to 15 decibels lower because traffic noise was a function of total
traffic flow (AADT) in the period 6am to midnight. He said that outside that period
traffic flows were much lower giving traffic noise in the 40s and 50s. Mr. Tiernan asked
how noise was measured and Mr Dilworth explained the basis for the LA 10 18 hour
parameter presently used in Ireland for traffic noise measurements and how there was no
rule of thumb for relating noise to the distance a house was from a road, saying it
depended on variables like traffic flows, traffic speeds, gradients, HGV %s, topography,
screening, weather extremes etc..
Mr. Tiernan asked where the sampling points were in the Cannistown area and
Mr.Dilworth referred to these and explained why locations were selected and that unusual
noise sources would mean a particular location would not be used, as well as the
difference between baseline measurements and modeled noise levels. Mr. Dilworth said
that one of the difficult results to get across to people was where the noise level at a
prediction location showed a decrease, which he said would come from a redistribution of
traffic patterns by traffic moving off a local road and onto a new road. He said that the
cumulative effect of this traffic removal to another road some 100 to 200 metres distant
giving a benefit was a hard point to get across. Mr. McIntyre said that the Cannistown
Residents Association believed that figures lower than 68 dB should be used and that best
practice meant EU directives should be put into place now rather than having in the
future, as taxpayers, to pay for a modification to the presently proposed mitigation
651
measures. He said that environmental noise had several negative effects on humans and
the most important of these was annoyance and that it would annoy him to have a slip
road 170 metres from his back door where now he had green fields. He said it was also
the cause of mental stress, hearing damage, blood pressure and that he could not think of
one positive effect other than that he was actually in favour of the motorway but said he
could not abide a system whereby they had to accept design specifications knowing that
these would have to be changed within 3, 7 or 12 years time and at great expense which
could be avoided if common sense prevailed.
Mr. Tiernan said that as a community they accepted the motorway was going through, but
they wanted assurances that it would have the least impact and that their concerns about
drainage, noise and the safety of their community and children would be taken on board.
89. 3. Cross-examined by Jim McIntyre, Boyne Hill, Navan on his own behalf :
Mr. McIntyre said his house was located at position P10 in Figure 5.1.1 of Vol. 5A of the
EIS on the Kilcarn Road and that his queries would follow on from where they had
reached when he was part of the Cannistown delegation and asked if the L10 18hour
dB(A) was the most commonly used parameter for assessing traffic noise in a european
or worldwide context. Mr. Dilworth said it was the only one used in a national context
but said the LAeq parameter was more widely used in a european context. Mr. McIntyre
referred to the reference to traffic noise assessment on the NRA website, which said the
most commonly used parameter was the L10 18hour dB(A), but Mr. Dilworth said they
were probably referring to the Irish context and when Mr. McIntyre said the website
intent was misleading as it implied that parameter was the most commonly used in
Europe, Mr. Dilworth replied that was a matter he should take up with the NRA. Mr.
McIntyre asked if the UK were the only other country using the CRTN 68 level and when
Mr. Dilworth confirmed that was so, he suggested that Australia used a figure of 55 with
mitigation at levels above 63, and when Mr. Keane intervened to ask what parameter was
the 55, he said it was in LAeq which would be about 58dB. Mr. Dilworth said that a freefield
55LAeq was about 60 LA10 façade which was the parameter they were talking
about.
Mr. McIntyre asked if the Australian criteria were to be applied what additional
mitigation measures would need to be applied to the proposed route between Clonee to
Kells. Mr. Dilworth said that the extent of additional measures would be a function of the
final selection of the criteria and that the Irish figure of 68 dB was 63LAeq in terms of
our European neighbours, a number of whom had limits of 60 LAeq, so that a further 3db
might need an alternative surfacing or barrier screening but he could not say if it would
require a 20% more mitigation or whatever. Mr. McIntyre asked if he accepted it would
require more mitigation if a level like Australia were used and Mr. Dilworth said that was
likely but said the Australian level of 55 was aspirational and they had a higher level
where mitigation was required which was, he thought, the 63 mentioned. He said the
lowest European level he was aware of was 55 and that the majority hovered around 60
but with lower night time limits. Mr. McIntyre then suggested that if the average
European limit was applied that would require significantly more mitigation than was
652
proposed for the slip road passing his house into Navan and Mr. Dilworth agreed but said
that a detailed assessment would be needed to determined the exact amount. He said that
if the goal posts were moved by 3 to 5 decibels it followed that additional mitigation
would be required.
Mr. McIntyre then quoted from a TRL company statement employed by the EU to
conduct a survey into effects of noise and as a briefing document for the 2002 EU
Directive which referred to the basis of the UK index of 68 dB as coming from the early
1970s when equipment for the LAeq measurement of noise energy had not been
developed and he suggested the criteria had outlived its usefulness and said that it was
only be used in Ireland now to minimise the amount of noise mitigation that had to be
applied along new roads. He said he had purposefully applied for planning permission for
his house so that it was equally distant from the Cannistown and Borallion (Ballybatter)
Roads so he could stay as far away from road noise as possible but now the slip road
would be 170 metres from him at the nearest corner. He asked what level of noise would
be expected at his house and Mr. Dilworth replied that while the level would depend on
distance, geometry and ground cover, he would expect it to be in the high 50s. Mr.
McIntyre asked what his present noise level, without the motorway, was in his very rural
area with only distant traffic and Mr. Dilworth said he would expect that it could be in the
30s to 40s and Mr. McIntyre suggested it was in the low to mid 30s which would mean a
20 decibel increase in noise levels passing his back door. When Mr. Dilworth agreed it
would be of that order, Mr. McIntyre asked what mitigation measures would have to be
pout in place if the EU legislation came into force before the motorway came to be built
and figures of 55/60 were set. Mr. Dilworth replied that it was probable that none would
be required since the level at his property would be around 55 LAeq and the criterion he
had mentioned would be below that since it was measured at the façade. When Mr.
McIntyre asked if he was a border line case at 170 metres for the expected EU legislation,
Mr. Dilworth said it was only a possible new limit and that it might be left to each
Member state to set their own limits.
Mr. McIntyre referred to the likelihood of the Directive setting limits on noise and Mr.
Dilworth accepted that while 55 was one of the figures being discussed, his own personal
view was for 60 being the more likely figure if a limit was eventually set by the EU. Mr.
McIntyre referred to the noise mapping process in CRTN and asked if that was done for
the M3 but Mr. Dilworth said that was the terminology used and that a model was done
for the entire route with the baseline measurements only taken when the meteorological
conditions specified were complied with. When Mr. McIntyre suggested the EU
Directive required noise mapping by the state by 2005, Mr. Keane intervened to say the
Directive did not say noise mapping had to be completed before 2005 as there were a
series of dates in it .
Mr. McIntyre asked what mitigation measures were proposed for the section of the
Kilcarn slip road behind his house and when Mr. Dilworth said there were none as the
predictions were less than 68dB, he suggested the raised road should worsen the situation
but Mr. Dilworth said that was taken account of. Mr. McIntyre asked if the proposed
screening and planting there had anything to do with noise or was it just a visual exercise
653
and Mr. Dilworth confirmed it was not noise related. Mr. McIntyre concluded by
referring again to the NRA website but Mr. Dilworth said he could not comment on that
wording as it was something to be directed to the NRA. The Inspector asked if he had
been given a copy of the Council's proposed adjustment to the noise criteria and when
Mr. McIntyre said that he had not, Mr. Keane said they would get him a copy and the
Inspector reminded Mr. Keane to supply a copy to the Bellinter Residents Association as
well.
90. Evidence of Bill O'Kelly-Lynch, Socio-economic Consultant,
on behalf of the Council :
90. 1. Examined by Esmond Keane B.L. for the Council :
Note -- Mr. O'Kelly-Lynch had previously given evidence on the Clonee to Dunshaughlin
Section in Section 30.1. of this Report and as the first two paragraphs are also relevant to
Navan By-pass Section they are not repeated here.
Mr. O'Kelly-Lynch said that the improved road network from the Scheme would provide
significant benefits at regional and sub-regional levels with travel times and transport
costs being reduced and with safer journeys which would enhance economic
development, stimulate tourism activity and improve accessibility for recraetional and
cultural facilities. He said that at local level there would be positive and negative benefits
with positive benefits being experienced by communities along the N3 corridor by the
cleaner and safer environment from the reduced traffic volumes and that the residents of
Navan would enjoy benefits from being by-passed, with the reductions in the through
traffic giving relief from severance and improved amenity and safety. He said that the
improved traffic circulation and better road network would reduce delivery times which
would benefit the business community in the Navan area from the increased productivity
and greater reliability in the transport of goods and services. He said the accessibilty of
schools and recreational facilities would be significantly improved and the social
environment would be enhanced and that the reduced traffic would also create a safer and
quieter environment for people living and working on the approaches to Navan
Mr. O'Kelly-Lynch said that some businesses particularly those on the N3, the N51and to
some extent on the proposed cul-de-sacs would suffer from a reduction in passing trade
but that in the long term the improved traffic circulation and reduced congestion in Navan
would make this more attractive for shopping and business and the scheme was expected
to have a nett positive impact there in the medium to longer term. He said the improved
road network would increase the attractiveness of Navan and its environs for commuter
housing and retail / commercial development with pressure for out of town retail /
commercial developments near the proposed Interchanges.
He said some of the road alterations in the scheme would have negative social impacts on
the local community, particularly the road closures and road realignments on Swan Lane;
R161, Trim Road; the Robinstown road, L4007-0; the N51 Athboy Road, the Boyerstown
654
road L 80008-20; Halltown road L 80091-16 and the Durhamstown road L 4005-11. He
said that measures to mitigate some of the negative impacts had been identified and these
included footpaths to reduce severance impacts for local communities and signs to reduce
impacts for businesses due to the loss of passing trade with measures to reduce negative
impacts during construction also identified. He concluded by saying that with the
implementation of mitigation measures the advantages of the Scheme considerably
outweighed the disadvantages with residual impacts being, in the main, minor. He said
that any major or moderate impact remaining after mitigation would only affect relatively
few individuals and that the nett socio-economic impact for society as a whole would be
positive.
91. Evidence of Richard Nairn, NATURA Environmental Consultants,
for the Council :
91. 1. Examined by Esmond Keane B.L. for the Council :
Mr. Nairn, who had given evidence on Ecology in the Dunshaughlin to Navan Section,
said he was the Managing Director of NATURA who were natural environmental
Consultants and his firm had been engaged by MC O'Sullivans to deal with the Flora and
Fauna aspects of the EIS, except for fish or fisheries which would be dealt with by other
specialists. ( Note-- Some of his general evidence was the same as he had already given
for the Dunshaughlin to Navan Section and is not repeated here for the Navan By-pass
Section.)
He said that all habitats along the proposed route were surveyed during September 2000
and classified with the dominant species recorded and hedgerows evaluated on a 3 point
scale of high, medium or low ecological value. He said that an inventory of all trees along
the line of the route was made in February 2001 and it was unlikely this environment had
changed since then. He said mammals and birds were assessed during the habitat surveys
using a combination of direct sightings and observations of signs, with some additional
field visits in September 2001 to locate badger setts and areas of high badger activity and
to carry out bat surveys in building scheduled for demolition.
Mr. Nairn then described the route and said there were no designated areas along the
route but there were 3 proposed NHAs within 10kms.of the route, none being affected by
the M3. He said the habitat survey showed improved agricultural grassland and arable
crops as the dominant habitat along the route, these being highly modified habitats and
were of low ecological value. He said areas of semi-natural grasslands were scattered
along the route and were either heavily grazed and species poor or transient as in the case
of set-aside. He said the most significant habitat recorded in the survey was an area of
wet grassland at chn. 48400 approximately, in Ardbraccan where the high species
diversity and low levels of grazing meant the site was of high local ecological value. He
said a further area of wet grassland occurred beside the River Boyne at Kilcarn Bridge
and while species diversity was low it formed an integral part of the Boyne floodplain
and was of moderate local ecological value.
655
He said other habitats of moderate ecological value included relatively undisturbed areas
of grassland, scrub and woodland at the northern end of the Athboy Link Road at chn.
1650 to 2300 and at Athboy Roundabout. He said woodland occurred in small bands or
blocks along the route and was mainly broadleaved woodland derived from past planting,
and that there were also areas of scrub and an immature broadleaved plantation of low
ecological value. He said hedgerows were a significant feature of the landscape along the
route and these were one of the main semi-natural habitats for flora and fauna in the
expanses of intensively managed farmland. He said while most were of low to moderate
local ecological value, there were hedgerows of high ecological value at a number of
locations.
Mr. Nairn said that a number of treelines occurred along the route and that these were of
moderate local ecological value due to the presence of mature broadleaved trees
providing valuable habitat for invertebrates, bats and birds. He said all trees of greater
than 30 cm. diameter at breast height along the route were recorded as part of a tree
inventory and that 624 trees would be felled during the road construction and that most of
the trees were in hedgerows and treelines along field boundaries and beside roads with
most being native species. Mr. Nairn said that the route crossed a number of watercourses
in lowland farmland, all being small streams in the upper reaches and all of low to
moderate local ecological value. He said that no Otter signs were noted during the field
survey.
He said Bat activity was noted at a number of locations with the species present being
Brown long-eared bats, Pipistrelles and Daubenton's bat and that a house at site 4 was
identified as a Bat roost, wth feeding bats being detected along treelines and along the
Boyne in the region of Kilcarn Bridge.
Mr.Nairn said that Badger tracks were noted at two locations but no breeding setts were
located during the survey but that this did not preclude the presence of breeding badgers
in the area as setts could be dispersed and were usually well-concealed in hedgerows,
scrub areas or woodland. He said no signs of Deer were noted during the field survey but
it was likely they passed through or feed in fields along the route occasionally and he said
high levels of deer activity were observed in the narrow stretch of woodland at
Ardsallagh. He said that a wide range of common bird species was observed but that a
greater diversity of species typically associated with the range of available habitats would
be expected in other seasons than the time of the survey.
Mr. Nairn said the impacts of the proposed route on improved grassland and arable land,
both of low ecological value, would not be significant and that on areas of semi-natural
grassland and wet flushes would be minor negative and only of local significance. He
said there would be a major negative impact of local significance on the wet grassland
area at chn. 48400, with most of this habitat being lost through construction, drainage and
re-direction of the water source. He said the loss of treelines would constitute a moderate
negative impact, except for the 250 metre stretch of beech treeline along both sides of the
Trim Road where the impact would be of major negative local significance.
656
He said the route would impact on minor watercourses at 4 main locations which would
be of a temporary nature with riparian and bankside vegetation disturbed during
construction, and that there would be some permanent loss of bankside vegetation where
watercourses were culverted.
He said there would be a negative impact on animal and bird populations near the
proposed road from disturbance during the construction and, to a lessor extent, from its
operation and also with negative impacts from the loss of areas of semi-natural habitat
for feeding, breeding and cover; and the creation of barriers to animal movement, habitat
fragmentation, severance of territories and isolation of populations. He said the road
construction would have a negative impact on Bats through the loss of foraging habitat
and roosting sites, with flight paths between foraging and roosting sites interrupted by the
removal of both hedgerows and treelines. He said lighting associated with the road might
disturb the feeding behaviour of some species or might discourage Bats from using
adjacent habitats and that potential breeding and hibernation sites would also be lost by
the removal of some buildings.
Mr. Nairn said road construction was likely to lead to fragmentation of the home ranges
of some larger mammals such as Deer and Badger but this was not significant as no large
concentrations of either species were affected and he said that animals would become
habituated to road traffic in due course.
Mr. Nairn then referred to the mitigation measures proposed and said there would be no
hedgerow removal during the months of March to June inclusive to avoid impacts on
breeding birds, and that trees and hedgerows being retained would be fenced at the
canopy line prior to construction. He said buildings with bat roosts would not be
demolished or disturbed during the months of June to August, the breeding season, or
November to March, the hibernation season. He said the old stone railway bridges near
chn. 40000 on the M3 at Cannistown and at chn. 1650 on the Kilcarn Link would be
retained as these were likely to be used as Bat roosts. He said that impacts on the wetland
areas at chn. 48400 would be reduced by maintaining the hydrological integrity of the
system and by allowing water to percolate under the road
He said that impacts on hedgerows and tree lines intersected by the new road would be
reduced by minimising the working area around these habitats with the working area
defined before siteworks by the erection of a fence to define the limits of the siteworks.
He said that any trees and hedgerows being retained within the site works would be
fenced at the outset, with the fence line set at the outer canopy line of the trees and that
ground levels would not be altered in any way within that fenced off area.
Mr. Nairn said that bankside vegetation would be left intact where possible and that
adequate fencing would be provided by fencing it off prior to construction, with the
fences set at a minimum distance of 5 metres from the bank of the watercourse or the
edge of the woodland canopy whichever was greater. He said that where natural bankside
vegetation had to be removed it would be pulled back from the river edge by machinery
657
operating from the bank. He said that where temporary diversion of a watercourse was
required that should be done prior to removing bankside vegetation and where permanent
diversion was required, the existing vegetation would be removed in sods to be re-planted
on the new river banks. He said that no works would be conducted in bankside vegetation
during the March to June period if suitable habitat for breeding birds existed there and
that transplanting of bankside vegetation would be conducted during the dormant season,
except where salmonid restrictions were in force when transplanting would be in the
period August to November.
Mr. Nairn said that replanting or rehabilitation of banksides would follow a sensitive
grading of the banks to replicate topography and that planting would use native species
and would follow a natural zonation appropriate to the river profile. He said temporary
deer and hare proof fencing would be erected to protect newly planted areas. He said
hedgerows and treelines would be retained, where possible, for their value as ecological
corridors for wildlife in general, and for Bats in particular, and that mature trees would be
retained, where possible, to minimise unintentional destruction of Bat roosts. He said that
no special mitigation measures were required for improved grassland, arable land or areas
of semi-natural grassland that were of low ecological value.
Mr. Nairn said that where the removal of hedgerows, treelines and mature trees could not
be avoided then compensatory measures, including the re-planting of hedgerows and
treelines along new or modified field boundaries adjacent to the road, would be
undertaken.
He said that areas of severed land would be planted with native broad-leaved trees, or set
aside to allow for natural re-vegetation, to compensate for the loss of woodland and
habitat fragmentation of ecological value and that those areas would be designed towards
ensuring ecological connections or wildlife corridors were maintained between existing
areas of woodland, hedgerow, treelines and watercourses.
He said that where buildings containing bat roosts were to be demolished, bats must be
excluded prior to demolition and this can only take place under a licence from Duchas
and in the presence of a bat specialist and should not be done between the months of June
to August ( Breeding season) or November to March (Hibernation season). He said that
where the removal of buildings or mature trees could not be avoided, Bat boxes would be
erected in appropriate locations in the area, at least one month in advance of any
disturbance, to compensate for the loss of known or potential Bat roost sites.
92. Evidence of Jean Clarke, Associate, MC O'Sullivans, Consulting Engineers
for the Council :
92. 1. Examined by Esmond Keane B.L. for the Council :
Ms Clarke said she would be dealing with the Non - agricultural Material Assets and that
she had a Degree in Science from UCG and a M. Sc. in Environmental Science from
658
TCD and had worked extensively on waste planning and environmental management as
an Associate in MC.O'Sullivans.
Ms Clarke said there were some non-agricultural holdings which would be impacted by
the landtake and the alteration of access and these included residences, commercial
properties, recreational facilities and other non-agricultural lands which would be directly
affected by the proposed road. She said the compensation issues would be dealt with by
the Council at a later stage if the CPO were approved. She said that the assessment was
done by a combination of a desk study, orthophotography and a field study carried out in
May 2001 along the route of the proposed Navan By-pass with each property affectd
being classified as residential, commercial, recreational or non-agricultural land and that
properties only loosing the road bed were not included.
Ms Clarke said 3 occupied dwellings were being acquired and a further 10 properties
would be affected by a partial acquisition of their landholding and that no commercial
properties were being acquired but one would be affected by the acquisition of part of its
holding. She said one field classified as non-agricultural would be acquired and a further
5 green areas would lose of part of the area and that 4 private driveways would be
affected by acquisition of par